File #: 2000-0114    Version: 1 Name: Change Order No. 3 - Ormond Road Raising
Type: Ordinance Status: Enacted
File created: 2/21/2000 In control: Parish Council
On agenda: Final action: 3/20/2000
Enactment date: 3/20/2000 Enactment #: 00-3-3
Title: An ordinance approving and authorizing the execution of Change Order No. Three (3) for Parish Project No. P960311 Ormond Road Raising to increase the contract amount by $145,000 and to increase the contract time by 250 days.
Sponsors: Albert D. Laque, Department of Public Works
Indexes: DRO (Ormond Road Raising)
Attachments: 1. 2000-0114 Change Order-Final, 2. 2000-0114 Final Ord 00-3-3 With Change Order

2000-0114

INTRODUCDED BY:  ALBERT D. LAQUE, PARISH PRESIDENT

                                                                  (DEPARTMENT OF PUBLIC WORKS)

 

ORDINANCE NO. _____

Title

An ordinance approving and authorizing the execution of Change Order No. Three (3) for Parish Project No. P960311 Ormond Road Raising to increase the contract amount by $145,000 and to increase the contract time by 250 days.

Body

THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:

                     SECTION I.                     Ordinance No. 99-6-19 adopted June 21, 1999 by the

St. Charles Parish Council, approved and authorized the execution of a contract

with Hebert Brothers Engineers, Inc. for the construction of Ormond Road

Raising in the amount of $528,505.93. 

                     SECTION II.                     That an Ordinance No. 99-11-4 adopted November 2, 1999

approved and authorized the execution of Change Order No. One (1) for the

Ormond Road Raising Contract to increase the contract amount by $54,202.60

because of the unsuitable soil conditions.

                     SECTION III.That an Ordinance No. 00-1-3 adopted January 11, 2000

approved and authorized the execution of Change Order No. Two (2) for the

Ormond Road Raising Contract to increase the contract amount by $9,942.97

and to increase the contract time by 73 calendar days for the relocation of the

drainage trunk line and required traffic signage.

                     SECTION IV.That it is necessary to amend the contract to reimburse the

 Contractor for shutdown time and remobilization.

                     SECTION V.                      That it is necessary to increase the contract amount by $145,000

and the contract time by 250 calendar days.

NOW, THEREFORE, BE IT ORDAINED, THAT WE, THE MEMBERS OF THE

ST. CHARLES PARISH COUNCIL, do hereby approve and authorize the execution

of Change Order No. Three (3) to the contract for the Ormond Road Raising Contract

and to increase the contract amount by $145,000 and the contract time by 250 calendar

days.

BE IT FURTHER ORDAINED, that the Parish President is hereby authorized to execute this Change Order to the contract.

Vote

                     The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:

 

 

 

                     And the ordinance was declared adopted this _____ day of ____________, ___,

To become effective five (5) days after publication in the Official Journal.

 

 

CHAIRMAN:______________________________________________

SECRETARY:_____________________________________________

DLVD/PARISH PRESIDENT:_________________________________

APPROVED:______________ DISAPPROVED:__________________

 

 

PARISH PRESIDENT:______________________________________

RETD/SECRETARY:_______________________________________

AT:_______________RECD BY: _____________________________