File #: 2014-0016    Version: 1 Name: Change Order No. 1 (Final) for Parish Project No. P080502-4, East Bank Master Drainage Plan - Dunleith Canal Level Recharge System Project to decrease the contract amount by $26,027.27 and increase 62 days
Type: Ordinance Status: Enacted
File created: 1/21/2014 In control: Parish Council
On agenda: Final action: 2/3/2014
Enactment date: 2/3/2014 Enactment #: 14-2-4
Title: An ordinance approving and authorizing the execution of Change Order No. 1 (Final) for Parish Project No. P080502-4, East Bank Master Drainage Plan - Dunleith Canal Level Recharge System Project to decrease the contract amount by $26,027.27 and increase the contract time by 62 days.
Sponsors: V.J. St. Pierre Jr., Department of Public Works
Indexes: DRO (Dunleith Canal Level Recharge System)
Attachments: 1. 2014-0016 Change Order Dunleith Canal Level Rechg, 2. 2014-0016 Final Ord 14-2-4 with Change Order
Related files: 2018-0342, 2018-0233, 2018-0033, 2017-0414, 2016-0290, 2010-0384, 2008-0482, 2009-0062, 2011-0167, 2008-0249, 2008-0441, 2009-0123, 2010-0156, 2011-0052, 2012-0132, 2012-0282, 2012-0297, 2013-0002, 2013-0157, 2014-0001, 2015-0008, 2015-0009, 2015-0087, 2020-0177, 2019-0098, 2019-0164, 2020-0042
2014-0016
INTRODUCED BY:      V.J. ST. PIERRE, JR., PARISH PRESIDENT
                  (DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO.                   
Title
An ordinance approving and authorizing the execution of Change Order No. 1 (Final) for Parish Project No. P080502-4, East Bank Master Drainage Plan - Dunleith Canal Level Recharge System Project to decrease the contract amount by $26,027.27 and increase the contract time by 62 days.
Body
WHEREAS,      Ordinance No. 13-5-1 adopted May 6, 2013, by the St. Charles Parish Council, approved and authorized the execution of a contract with Volute, Inc. for Parish Project No. P080502-4, East Bank Master Drainage Plan - Dunleith Canal Level Recharge System in the amount of $181,419.00; and,
WHEREAS,      the decrease in contract amount resulted from one (1) deleted bid line item in the amount of -$35,000.00, and an addition of three (3) bid line items in the amount of +$789.73, and a change in four (4) bid line items in the amount of +$8183.00; and,
WHEREAS,      the decrease in the contract amount was a result of adjusted and deleted bid line item quantities and materials; and,
WHEREAS,      due to delays in equipment delivery, the contract time needs to be extended by 62 days.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS,
SECTION I.      That Change Order No. 1 (Final) for Parish Project No. P080502-4, East Bank Master Drainage Plan - Dunleith Canal Level Recharge System Project to decrease the contract amount by $26,027.27 and to increase the contract time by 62 days is hereby approved and accepted.
SECTION II.      That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.
Vote
      The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
 
 
 
 
      And the ordinance was declared adopted this              day of                      , 2014, to become effective five (5) days after publication in the Official Journal.
 
 
 
CHAIRMAN:______________________________________________
SECRETARY:_____________________________________________
DLVD/PARISH PRESIDENT:_________________________________
APPROVED:______________ DISAPPROVED:__________________
 
PARISH PRESIDENT:______________________________________
RETD/SECRETARY:_______________________________________
AT:_______________ RECD BY: _____________________________