Title: An ordinance approving and authorizing the execution of Change Order No. 1 for Parish Project No. S080501-1, Destrehan WWTP Rehabilitation Phase I Headworks to increase the contract amount by $19,993.00.
Sponsors: V.J. St. Pierre Jr., Department of Wastewater
Indexes: SPW (Destrehan WWTP Rehabilitation Ph. I Headworks)
Attachments: 1. 2009-0244 Change Order-F, 2. 2009-0244 Final Ord 09-7-8 with Change Order
Related files: 2012-0185, 2008-0455, 2011-0201, 2009-0100, 2010-0413, 2010-0414, 2009-0306, 2009-0331, 2011-0354, 2011-0357, 2012-0076, 2008-0441
2009-0244
INTRODUCED BY:      V.J. ST. PIERRE, JR., PARISH PRESIDENT
                  (DEPARTMENT OF WASTEWATER)
ORDINANCE NO.  _____            
Title
An ordinance approving and authorizing the execution of Change Order No. 1 for Parish Project No. S080501-1, Destrehan WWTP Rehabilitation Phase I Headworks to increase the contract amount by $19,993.00.
Body
WHEREAS,      Ordinance No. 08-12-2, adopted December 1, 2008, by the St. Charles Parish Council, approved and authorized the execution of a contract with Cajun Constructors, Inc. for Destrehan WWTP Rehabilitation Phase I Headworks in the amount of $349,500.00; and,
WHEREAS,      the majority of the cost associated with this change order is due to the unforeseen concrete damage beyond two inches of depth; and,
WHEREAS,      it is necessary to amend the contract deleting one item, reducing another item, and adding three additional items, resulting in an increase to the contract amount by $19,993.00 and increasing the contract time by 40(forty) days.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I.      That Change Order No. 1 for Parish Project No. S080501-1, Destrehan WWTP Rehabilitation Phase I Headworks to increase the contract amount by $19,993.00 and the contract time by 40 days is hereby approved.
SECTION II.      That the Parish President is hereby authorized to execute said Change Order No. 1 on behalf of St. Charles Parish.
Vote
      The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
 
 
 
 
      And the ordinance was declared adopted this _______ day of __________, 2009, to become effective five (5) days after publication in the Official Journal.
 
 
 
CHAIRMAN:______________________________________________
SECRETARY:_____________________________________________
DLVD/PARISH PRESIDENT:_________________________________
APPROVED:______________ DISAPPROVED:__________________
 
PARISH PRESIDENT:______________________________________
RETD/SECRETARY:_______________________________________
AT:_______________ RECD BY: _____________________________