Title: An ordinance authorizing St. Charles Parish to enter into an 'Assignment of Flood Closure Structure Operation and Maintenance, WBV-75' with the Coastal Protection and Restoration Authority for the 'West Bank and Vicinity, New Orleans, Louisiana Hurricane Project, WBV-75, Western Tie-In BNSF Railroad Crossing, St. Charles Parish, Louisiana'.
Sponsors: V.J. St. Pierre Jr., Department of Public Works
Indexes: Floods, Hurricane Protection Levee (WBV - Jefferson to Davis), Railroad
Attachments: 1. 2015-0374 WBV 75 BNSF Contract exec 11-06-21, 2. 2015-0374 Assignment-F, 3. 2015-0374 Final Ord 15-11-5 with Assignment
Related files: 2008-0183, 2010-0248, 2011-0279, 2012-0073, 2015-0375

2015-0374

INTRODUCED BY:                     V.J. ST. PIERRE, JR., PARISH PRESIDENT

                                                               (DEPARTMENT OF PUBLIC WORKS)

ORDINANCE NO.  ____________

Title

An ordinance authorizing St. Charles Parish to enter into an ‘Assignment of Flood Closure Structure Operation and Maintenance, WBV-75’ with the Coastal Protection and Restoration Authority for the ‘West Bank and Vicinity, New Orleans, Louisiana Hurricane Project, WBV-75, Western Tie-In BNSF Railroad Crossing, St. Charles Parish, Louisiana’.

Body

WHEREAS,                     on June 21, 2011, the Office of Coastal Protection and Restoration executed a certain Flood Closure Structure Construction and Maintenance Agreement with BNSF Railway Company in order to construct, operate and maintain a hurricane protection floodgate and appurtenances for the ‘West Bank and Vicinity, New Orleans, Louisiana Hurricane Project, WBV-75, Western Tie-In BNSF Railroad Crossing, St. Charles Parish, Louisiana’ (Project); and,

WHEREAS,                     on June 21, 2011, the Office of Coastal Protection and Restoration entered into an Easement Agreement for the West Bank & Vicinity, Louisiana Project, St. Charles Parish, Louisiana (C&M Agreement), which allowed the installation of railroad floodgates across the BNSF Railway’s property, being constructed in accordance with the Flood Closure Structure Construction and Maintenance Agreement; and,

WHEREAS,                     in accordance with the La. R.S. 38:101(C), upon completion of the construction of hurricane protection projects, the operation and maintenance of the hurricane protection system is to be transferred to the local governments; and,

WHEREAS, pursuant to Article V, Section 13(b) of the Flood Closure Structure Construction and Maintenance Agreement, the term and conditions of the flood gates operations and maintenance shall be assumed by St. Charles Parish upon completion; and,

WHEREAS,                     the Project is now complete, and the Coastal Protection and Restoration Authority of Louisiana wishes to enter into an ‘Assignment of Flood Closure Structure Operation and Maintenance, WBV-75’ (Assignment) per letter dated August 24, 2015; and,

WHEREAS,                     the Assignment would transfer from the Coastal Protection and Restoration Authority all of its rights under the Flood Closure Structure Construction and Maintenance Agreement and the Easement Agreement to St. Charles Parish.

THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:

SECTION I.                     there is hereby a public need for St. Charles Parish to enter into the ‘Assignment of Flood Closure Structure Operation and Maintenance, WBV-75’ to operate and maintain said flood structures.

SECTION II.                     That St. Charles Parish does hereby assume all of the Coastal Protection and Restoration Authority’s duties and obligations under the Flood Closure Structure Construction and Maintenance Agreement and the Easement Agreement for the ‘West Bank and Vicinity, New Orleans, Louisiana Hurricane Project, WBV-75, Western Tie-In BNSF Railroad Crossing, St. Charles Parish, Louisiana’.

SECTION II.                     That the Parish President is hereby authorized to execute any and all documents necessary to complete said ‘Assignment of Flood Closure Structure Operation and Maintenance, WBV-75’.

The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:

 

 

 

 

And the ordinance was declared adopted this _______ day of _____________, 2015, to become effective five (5) days after publication in the Official Journal.

 

 

CHAIRMAN:_________________________________________

SECRETARY:________________________________________

DLVD/PARISH PRESIDENT:____________________________

APPROVED:______________ DISAPPROVED:_____________

 

PARISH PRESIDENT:_________________________________

RETD/SECRETARY:__________________________________

AT:_______________ RECD BY: ________________________

MAN:________________