logo  ST. CHARLES PARISH, LA
File #: 2018-0292    Version: 1 Name: Construction Contract with Sealevel Construction, Inc. for Ellington Drainage Pump Station Project, as part of the West Bank Hurricane Protection Levee Project
Type: Ordinance Status: Enacted
File created: 10/15/2018 In control: Parish Council
On agenda: 11/5/2018 Final action: 11/5/2018
Enactment date: Enactment #: 18-11-1 AMENDED
Title: An ordinance to approve and authorize the execution of a Construction Contract with Sealevel Construction, Inc. for Project No. P080905-5D, grant reference Project No. H.013148, Ellington Drainage Pump Station Project, as part of the West Bank Hurricane Protection Levee Project, in the amount of $8,288,890.00.
Sponsors: Lawrence 'Larry' Cochran, Department of Public Works
Indexes: Hurricane Protection Levee (WB - Ellington), Public Works (Dept. of)
Attachments: 1. 2018-0292 Ellington Contract, 2. 2018-0292 Bid Tabulation - Ellington DPS, 3. 2018-0292 Introduction of Ordinance for Ellington Drainage Pump Station.pdf, 4. 2018-0292 Final Ord 18-11-1 with contract, 5. 2018-0292 Filed Ord 18-11-1 with Notice of Contract, 6. 2018-0292 Notice to Proceed, 7. 2018-0292 Completion-F, 8. 2018-0292 Acceptance-F
Related files: 2017-0354, 2018-0226, 2018-0324, 2019-0163, 2022-0356, 2020-0281, 2013-0339, 2021-0101, 2022-0063

2018-0292

INTRODUCED BY:                      LARRY COCHRAN, PARISH PRESIDENT

                                                               (DEPARTMENT OF PUBLIC WORKS)

ORDINANCE NO.                                                                  

Title

An ordinance to approve and authorize the execution of a Construction Contract with Sealevel Construction, Inc. for Project No. P080905-5D, grant reference Project No. H.013148, Ellington Drainage Pump Station Project, as part of the West Bank Hurricane Protection Levee Project, in the amount of $8,288,890.00.

Body

WHEREAS,                     sealed bids were received by St. Charles Parish on October 9, 2018 for Project No. P080905-5D, grant reference Project No. H.013148, Ellington Drainage Pump Station Project; and,

WHEREAS,                     Burk-Kleinpeter, Inc., Michael G. Jackson, P.E., the Engineer for the Project, has reviewed the bids and recommended that the Contract be awarded to the lowest responsive bidder, Sealevel Construction, Inc. in the amount of $8,288,890.00; and,

WHEREAS,                     the Ellington Drainage Pump Station Project, as part of the West Bank Hurricane Protection Levee Project, will provide flood protection to approximately 536 residences, 25 businesses, and 13 public buildings located within the Ellington watershed area; and,

WHEREAS,                     the Ellington Drainage Pump Station Project consists of the installation of a new Drainage Pump Station, intake channel and discharge over the newly constructed Ellington Levee system protecting the Ellington watershed area. The project includes the purchase and installation of four (4) each 116 cfs pumps, 250 hp electric motor per pump, standby generator, station concrete structure, access road, intake channel, discharge piping and basin, automated bar screen cleaners; and,

WHEREAS,                     Resolution No. 6313 adopted on November 13, 2017, approved the execution of an Intergovernmental Agreement with the State of Louisiana Department of Transportation and Development under the Statewide Flood Control Construction Program to provide 70% of the Construction costs up to $5,681,380.70 in funding for said project.

THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:

SECTION I.                     That the bid of Sealevel Construction, Inc., for the construction of Project No. P080905-5D, grant reference Project No. H.013148, Ellington Drainage Pump Station Project, as part of the West Bank Hurricane Protection Levee Project, is hereby approved and accepted, in the amount of $8,288,890.00.

SECTION II.                     That the Parish President is hereby authorized to execute said contract on behalf of the Parish of St. Charles.

The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:

 

 

 

 

                     And the ordinance was declared adopted this ______ day of ___________, 2018 to become effective five (5) days after publication in the Official Journal.

 

 

CHAIRMAN:_________________________________________

SECRETARY:________________________________________

DLVD/PARISH PRESIDENT:____________________________

APPROVED:______________ DISAPPROVED:_____________

 

PARISH PRESIDENT:_________________________________

RETD/SECRETARY:__________________________________

AT:_______________ RECD BY: ________________________