File #: 2010-0076    Version: 1 Name: C.O. No. 1 for Parish Project No P090103-3, Road Maintenance 2009, to add additional work in the amount of $246,807.98 to make full use of St. Charles Parish budgeted amount of $970,000
Type: Ordinance Status: Enacted
File created: 2/8/2010 In control: Parish Council
On agenda: Final action: 3/1/2010
Enactment date: 3/1/2010 Enactment #: 10-3-2
Title: An ordinance approving and authorizing the execution of Change Order No. 1 for Parish Project No P090103-3, Road Maintenance 2009, to add additional work in the amount of $246,807.98 to make full use of St. Charles Parish budgeted amount of $970,000.
Sponsors: V.J. St. Pierre Jr., Department of Public Works
Indexes: DRO (Road Overlay 2009)
Attachments: 1. 2010-0076 Change Order-F, 2. 2010-0076 Final Ord 10-3-2 with Change Order
Related files: 2009-0034, 2009-0477, 2010-0250
2010-0076
INTRODUCED BY:      V.J. St. Pierre, JR., PARISH PRESIDENT
                  (DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO.                          
Title
An ordinance approving and authorizing the execution of Change Order No. 1 for Parish Project No P090103-3, Road Maintenance 2009, to add additional work in the amount of $246,807.98 to make full use of St. Charles Parish budgeted amount of $970,000.
Body
WHEREAS,      Ordinance No. 09-12-16 adopted December 21, 2009 by the St. Charles Parish Council awarded construction of Parish Project No P090103-3, Road Maintenance 2009, to Barriere Construction Co, LLC; and,
WHEREAS,      since the bid provided by Barriere Construction Co. LLC, was $726,761.44; well below the $970,000 budgeted by St Charles Parish; St. Charles Parish wishes to expend the budgeted amount; and,
WHEREAS,      additional work was identified and St. Charles Parish wishes to have the work performed; and,
WHEREAS,      it is necessary to amend the contract to add the additional work and to adjust the original contract quantities with current quantities resulting in an increase to the contract amount by $246,807.98.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
      SECTION I.      That Change Order No. 1 for Parish Project No. No P090103-3, Road Maintenance 2009, to increase the contract amount by $246,807.98 is hereby approved.
      SECTION II.      That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
 
 
 
 
And the ordinance was declared adopted this ____  day of ________        , 2010, to become effective five (5) days after this publication in the official journal.
 
 
 
CHAIRMAN:_________________________________________
SECRETARY:________________________________________
DLVD/PARISH PRESIDENT:____________________________
APPROVED:______________ DISAPPROVED:_____________
 
PARISH PRESIDENT:_________________________________
RETD/SECRETARY:__________________________________
AT:_______________ RECD BY: ________________________