logo  ST. CHARLES PARISH, LA
File #: 2022-0356    Version: 1 Name: C.O. No.1 for the Ellington Structures-Kellogg Pump Station T-Wall Project No. (P080905-5F, CPRA Project No. BA-0244)
Type: Ordinance Status: Enacted
File created: 1/9/2023 In control: Parish Council
On agenda: 1/23/2023 Final action: 1/23/2023
Enactment date: Enactment #: 23-1-5
Title: An ordinance approving and authorizing the execution of Change Order No. 1 for the Ellington Structures-Kellogg Pump Station T-Wall Project No. P080905-5F, CPRA Project No. BA-0244, as part of the West Bank Hurricane Protection Levee Project, to increase the contract amount by $113,705.00 and increase the contract time by ninety (90) days.
Sponsors: Matthew Jewell, Department of Public Works
Indexes: Grants, Hurricane Protection Levee (WB - Ellington), Hurricane Protection Levee (WB - Kellogg Pump Station T-Wall), Public Works (Dept. of)
Attachments: 1. 2022-0356 10475-0344_Kellogg CO #001_Package, 2. 2022-0356 Final Ord 23-1-5 with change order
Related files: 2022-0063, 2018-0324, 2013-0339, 2018-0226, 2018-0292, 2022-0195, 2017-0354, 2019-0163, 2020-0281, 2020-0324, 2021-0101, 2024-0137

2022-0356

INTRODUCED BY:  MATTHEW JEWELL, PARISH PRESIDENT

(DEPARTMENT OF PUBLIC WORKS)

ORDINANCE NO.  ______________

Title

An ordinance approving and authorizing the execution of Change Order No. 1 for the Ellington Structures-Kellogg Pump Station T-Wall Project No. P080905-5F, CPRA Project No. BA-0244, as part of the West Bank Hurricane Protection Levee Project, to increase the contract amount by $113,705.00 and increase the contract time by ninety (90) days.

Body

WHEREAS,                     Ordinance No. 22-3-12, adopted March 21, 2022 by the St. Charles Parish Council, approved and authorized the execution of a contract with Sealevel Construction, Inc, for Ellington Structures - Kellogg Pump Station T-Wall, Project No. P080905-5F, CPRA Project No. BA-0244, in the amount of $4,323,888.00; and,

WHEREAS,                     Resolution No. 6522, adopted on November 16, 2020, approved an Intergovernmental Agreement with the State of Louisiana through the Coastal Protection and Restoration Authority Board to provide $2,500,000.00 in funding for construction costs for said project; and,

WHEREAS,                     Ordinance No. 08-10-7 adopted October 20, 2008 approved and authorized the execution of a Contract for Engineering Services with BURK-KLEINPETER, INC. for necessary professional engineering services associated with Parish Project No. P080905 St. Charles Parish West Bank Hurricane Protection Levee and Urban Flood Control; and,

WHEREAS,                     Change Order No. 1 is a result of changes within the scope of the contract to address Geotech conditions not previously identified and to adjust T-Wall design to fit field conditions within the Construction Contract resulting in the lengthening of 33 batter “H” piles; and,

WHEREAS,                     the increase in contract amount by $113,705.00 is a result of deletion of two (2) bid line items, the addition of two (2) new line items, and increase in quantity of one 91 (1) bid line item; and,

WHEREAS,                     the increase in contract time by ninety (90) days is due to delay caused by pile load test not meeting the required design tonnage, time required for additional engineering design, and time required for PDA test.

THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:

SECTION I.                     That Change Order No. 1 for the Ellington Structures - Kellogg Pump Station T-Wall Project No. P080905-5F, CPRA Project No. BA-0244 as part of the West Bank Hurricane Protection Levee Project, to increase contract amount by $113,705.00 and increase the contract time of ninety (90) days is hereby approved and accepted.

SECTION II.                     That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.

The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:

 

 

 

 

And the ordinance was declared adopted this _____ day of _____________, 2023, to become effective five (5) days after publication in the Official Journal.

 

 