Title: An ordinance approving and authorizing the execution of Change Order No. 1 with Barriere Construction Co., L.L.C. for Road Maintenance 2024-25 (Project No. P220501), to increase the contract amount by $626,929.15, bringing the total construction cost to $3,350,185.15, and to increase the contract time by twenty (20) calendar days.
Sponsors: Matthew Jewell, Department of Public Works
Attachments: 1. 2025-0299 20250922_P220501_Road Maintenance 24-25_Change Order 1_Partial Signature
Related files: 2025-0082, 2025-0001, 2022-0180, 2023-0250, 2024-0204

2025-0299

INTRODUCED BY:                     MATTHEW JEWELL, PARISH PRESIDENT

(DEPARTMENT OF Public Works)

ORDINANCE NO.  __________

Title

An ordinance approving and authorizing the execution of Change Order No. 1 with Barriere Construction Co., L.L.C. for Road Maintenance 2024-25 (Project No. P220501), to increase the contract amount by $626,929.15, bringing the total construction cost to $3,350,185.15, and to increase the contract time by twenty (20) calendar days.

Body

WHEREAS,                     Ordinance No. 22-7-2 adopted on July 5, 2022, by the St. Charles Parish Council, approved and authorized the execution of a Professional Services Agreement with Digital Engineering & Imaging, Inc., to perform planning services for the Road Maintenance 2022-23 (Project No. P220501), in the not to exceed amount of $316,728.72; and,

WHEREAS,                     Ordinance 23-9-2 adopted on September 25, 2023, by the St. Charles Parish Council, approved and authorized the execution of Amendment No. 1 to Ordinance 22-7-2, which approved the Professional Services Agreement with Digital Engineering & Imaging, Inc. to perform planning services for Road Maintenance 2022-23 (Project No. P220501), to add other related projects listed below (total engineering and inspection):

                     Project                                                                                                                              Total Price

                     Additional Asphalt Maintenance                                                               $126,205.00

                     Concrete Maintenance 2023-24 (P230803)                     $211,740.00

                     Willowdale Turn Lane (P230804)                                                               $98,235.00; and,

WHEREAS,                     Ordinance 24-6-16 adopted on June 17, 2024, by the St. Charles Prish Council, approved and authorized the execution of Amendment No. 2 to Ordinance 22-7-2, which approved the Professional Services Agreement with Digital Engineering & Imaging, Inc., to perform planning services for Road Maintenance 2022-23 (Project No. P220501), to add Road Maintenance 2024-25 (Project No. P220501), formerly Road Maintenance 2024, in the amount of $135,238.00; and,

WHEREAS,                     Ordinance 25-1-6 adopted on January 27, 2025, by the St. Charles Parish Council, approved and authorized the execution of Amendment No. 3 to Ordinance 22-7-2, which approved the Professional Services Agreement with Digital Engineering & Imaging, Inc., to perform planning services for Road Maintenance 2022-23 (Project No. P220501), Road Maintenance 2024-25 (Project No. P220501) in the amount of $90,086.00 and adjustments to the distribution of funds on Road Maintenance 2022-23 (Project No. P220501), Willowdale Turn Lane (Project No. P230804), and Concrete Maintenance 2023-24 (Project No. P230803); and,

WHEREAS,                     Ordinance 25-4-2 adopted on April 7, 2025, by the St. Charles Parish Council, approved and authorized the execution of Contract with Barriere Construction Co., L.L.C. for Road Maintenance 2024-25 (Project No. P220501), in the amount of $2,723,256.00; and,

WHEREAS,                     it is necessary to amend the construction contract for Road Maintenance 2024-25 (Project No. P220501), as additional roads and work items were added during construction; and,

WHEREAS,                     St. Charles Parish and Barriere Construction Co. L.L.C., have mutually agreed to increase the contract price by $626,929.15 for these additional items, bringing the total construction cost to $3,350,185.15, and to add twenty (20) calendar days to allow for completion of the additional work.

THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:

SECTION I.                     That Change Order No. 1 for Road Maintenance 2024-25 (Project No. P220501), to increase the contract amount by $626,929.15, bringing the total construction cost to $3,350,185.15, and to increase the contract time by twenty (20) calendar days is hereby approved and accepted.

SECTION II.                     That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.

The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:

 

 

 

 

And the ordinance was declared adopted this _______ day of ___________, 2025, to become effective five (5) days after publication in the Official Journal.

 

 

CHAIRMAN:                                                                                                          

SECRETARY:                                                                                                          

DLVD/PARISH PRESIDENT:                                                                                     

APPROVED :                       DISAPPROVED:                                           

 

PARISH PRESIDENT:                                                                                     

RETD/SECRETARY:                                                                                                           

AT:                        RECD BY: