File #: 1999-4819    Version: 1 Name: Change Order No. One (1) for the Davis-Barton Drainage Improvements for the West Bank Drainage Improvements increase contract by $100,279.00 and increase contract time by 45 calendar days
Type: Ordinance Status: Enacted
File created: 8/2/1999 In control: Parish Council
On agenda: Final action: 9/7/1999
Enactment date: 9/7/1999 Enactment #: 99-9-12
Title: An ordinance to approve and authorize the execution of Change Order No. One (1) for the Davis-Barton Drainage Improvements for the West Bank Drainage Improvements to increase the contract amount by $100,279.00 and increase the contract time by 45 calendar days.
Sponsors: Chris Tregre, Department of Public Works
Indexes: DRO (WB Drg. Imp., Davis/Barton Drg. Imp.)
Attachments: 1. 1999-4819 Change Order.pdf, 2. 1999-4819 Final Ord 99-9-12 with Change Order
Related files: 2000-0491
INTRODUCED BY:      CHRIS A. TREGRE, PARISH PRESIDENT
                  (DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO.  ____________
Title
An ordinance to approve and authorize the execution of Change Order No. One (1) for the Davis-Barton Drainage Improvements for the West Bank Drainage Improvements to increase the contract amount by $100,279.00 and increase the contract time by 45 calendar days.
Body
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I.      That Ordinance No. 98-9-5 adopted September 8, 1998, by the St. Charles Parish Council, approved and authorized the execution of a contract with Civil Construction Contractors, Inc. for the construction of the Davis-Barton Drainage Improvements for the West Bank Drainage Improvements in the amount of $1,725,120.00.
SECTION II.      That it is necessary to increase the original contract amount and increase the original contract time.
NOW, THEREFORE, BE IT ORDAINED, THAT WE, THE MEMBERS OF THE ST. CHARLES PARISH COUNCIL, do hereby approve and authorize the execution of Change Order No. One (1) to the contract for the Davis-Barton Drainage Improvements for the West Bank Drainage Improvements, to increase the contract amount by $100,279.00 and increase the contract time by 45 calendar days.
BE IT FURTHER ORDAINED, that the Parish President is hereby authorized to execute this Change Order to the contract.
Vote
The foregoing Ordinance having been submitted to a vote, the vote thereon was as follows:
 
 
 
 
And the ordinance was declared adopted this           day of                     , 1999, to become effective five (5) days after this publication in the official journal.
 
 
 
CHAIRMAN:                                                                            
SECRETARY:                                                                        
DLVD/PARISH PRESIDENT:                                               
APPROVED:                      DISAPPROVED:                       
 
 
PARISH PRESIDENT:                                                           
RETD/SECRETARY:                                                             