File #: 2025-0152    Version: 1 Name: Contract w/ Barriere Construction Co., LLC, for the Murray Hill and Destrehan Drive Drainage Improvements (Project No. P201001), in the amount of $2,112,258.00
Type: Ordinance Status: Public Hearing
File created: 5/19/2025 In control: Parish Council
On agenda: 6/2/2025 Final action:
Enactment date: Enactment #:
Title: An ordinance approving and authorizing the execution of a Contract with Barriere Construction Co., LLC, for the Murray Hill and Destrehan Drive Drainage Improvements (Project No. P201001), in the amount of $2,112,258.00.
Sponsors: Matthew Jewell, Department of Public Works
Attachments: 1. 2025-0152 Revised - Edits - Section 00500 Contract BCC Executed, 2. 2025-0152 P201001 - 2025.05.08 - Notice of Intent to Award - Executed, 3. 2025-0152 Corporate Resolution, 4. 2025-0152 Award Recommendation, 5. 2025-0152 Signed Bid Tab
Related files: 2021-0057

2025-0152

INTRODUCED BY:                     MATTHEW JEWELL, PARISH PRESIDENT

(DEPARTMENT OF PUBLIC WORKS)

ORDINANCE NO.  ___________

Title

An ordinance approving and authorizing the execution of a Contract with Barriere Construction Co., LLC, for the Murray Hill and Destrehan Drive Drainage Improvements (Project No. P201001), in the amount of $2,112,258.00.

Body

WHEREAS,                     Ordinance No. 21-3-3 adopted on March 15, 2021, by the St. Charles Parish Council, approved and authorized the execution of an Engineering Services Agreement with H. Davis Cole & Associates, LLC for providing all necessary services for the Murray Hill Drive and Destrehan Drive Drainage Improvements, Project No. P201001, in the amount not to exceed $232,400.00; and,

WHEREAS,                     sealed bids were received by St. Charles Parish on March 6, 2025, for the Murray Hill and Destrehan Drive Drainage Improvements (Project No P201001); and,

WHEREAS,                     H. Davis Cole & Associates, LLC, has reviewed the bids and recommends that the Contract be awarded to the lowest responsive and responsible bidder, Barriere Construction Co., LLC, in the amount of $2,112,258.00.

THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:

SECTION I.                     That the bid of Barriere Construction Co., LLC, for the construction of Murray Hill and Destrehan Drive Drainage Improvements (Project No. P201001), in the amount of $2,112,258.00 is hereby approved and accepted.

SECTION II.                     That the Parish President is hereby authorized to execute said Contract on behalf of St. Charles Parish.

SECTION III.                     A final Notice of Contract shall be printed and filed in place of the contract documents with the St. Charles Parish Clerk of Court and in the records of the St. Charles Parish Council.

The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:

 

 

 

 

And the ordinance was declared adopted this              day of                      , 2025, to become effective five (5) days after publication in the Official Journal.

 

 

CHAIRMAN:                                                                                                                               

SECRETARY:                                                                                                                               

DLVD/PARISH PRESIDENT:                                                                                     

APPROVED :                       DISAPPROVED:                                           

 

PARISH PRESIDENT:                                                                                                          

RETD/SECRETARY:                                                                                                           

AT:                        RECD BY: