An ordinance approving and authorizing the execution of Change Order No. 2 with Kass Bros., Inc., for Concrete Maintenance 2023-24 (Project No. P230803), to increase the contract amount by $328,314.80 and to increase the contract time by sixty (60) days.
Body
WHEREAS, Ordinance No. 22-7-2 adopted on July 5, 2022, by the St. Charles Parish Council, approved and authorized the execution of a Professional Services Agreement with Digital Engineering & Imaging, Inc., to perform planning services for the Road Maintenance 2022-23 (Project No. P220501), in the not to exceed amount of $316,728.72; and,
WHEREAS, Ordinance No. 23-9-2 adopted on September 25, 2023, by the St. Charles Parish Council, approved and authorized the execution of Amendment No. 1 to Ordinance No. 22-7-2, which approved the Professional Services Agreement with Digital Engineering & Imaging, Inc. to perform planning services for the Road Maintenance 2022-23 (Project No. P220501), adding Concrete Maintenance 2023-24 (Project No. P230803), in the amount of $211,740.00; and,
WHEREAS, Ordinance No. 24-7-19 adopted on July 22, 2024, by the St. Charles Parish Council, approved and authorized the execution of a Contract with Kass Bros., Inc., for Concrete Maintenance 2023-24 (Project No. P230803), in the amount of $914,593.10; and,
WHEREAS, Ordinance No. 24-12-4 adopted on December 2, 2024, by the St. Charles Parish Council, approved and authorized the execution of Change Order No. 1 with Kass Bros., Inc., for Concrete Maintenance 2023-24 (Project No. P230803), to increase the contract amount by $193,430.85 and increase the contract time by thirty-five (35) days; and,
WHEREAS, it is necessary to amend the contract and incorporate additional quantities added during construction that improved the quality of the roadway and to add the maintenance work on Ares Street, Scorpio Street, and Leo Street; and,
WHEREAS, St. Charles Parish and Kass Bros., Inc., have mutually agreed to increase the contract amount by $328,314.80 and increase the contract time by (60) calendar days to complete the work.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That Change Order No. 2 for Concrete Maintenance 2023-24 (Project No. P230803), to increase the contract amount by $328,314.80 and increase the contract time by sixty (60) days is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this ______ day of ____________, 2025, to become effective five (5) days after publication in the Official Journal.
CHAIRMAN:
SECRETARY:
DLVD/PARISH PRESIDENT:
APPROVED : DISAPPROVED:
PARISH PRESIDENT:
RETD/SECRETARY:
AT: RECD BY: