File #: 1999-5013    Version: 1 Name: Execution of Change Order No. One (1) for the Ama Pump Station and Force Main Project to allow the contractor, D & O Contractors, Inc., to directional drill portions of the contract at no additional cost or time to the owner.
Type: Ordinance Status: Enacted
File created: 11/15/1999 In control: Parish Council
On agenda: 12/6/1999 Final action: 12/6/1999
Enactment date: 12/6/1999 Enactment #: 99-12-11
Title: An ordinance to approve and authorize the execution of Change Order No. One (1) for the Ama Pump Station and Force Main Project to allow the contractor, D & O Contractors, Inc., to directional drill portions of the contract at no additional cost or time to the owner.
Sponsors: Chris A. Tregre, Department of Wastewater
Indexes: SPW (Ama Pump Station and Force Main)
Attachments: 1. 1999-5013 Change Order.pdf, 2. 1999-5013 Final Ord 99-12-11 with Change Order
Related files: 1999-4815

INTRODUCED BY:                     CHRIS A. TREGRE, PARISH PRESIDENT

                                                               (DEPARTMENT OF WASTEWATER)

ORDINANCE NO.  ____________

title

An ordinance to approve and authorize the execution of Change Order No. One (1) for the Ama Pump Station and Force Main Project to allow the contractor, D & O Contractors, Inc., to directional drill portions of the contract at no additional cost or time to the owner.

body

THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:

SECTION I.                     That Ordinance No. 99-9-8 adopted September 7, 1999, by the St. Charles Parish Council, approved and authorized the execution of a contract with D & O Contractors, Inc. for the construction of the Ama Pump Station and Force Main Project in the amount of $1,538,117.30; and,

SECTION II.                     That it is necessary to allow the contractor to directional drill portions of the contract at no additional cost or time to the owner.

NOW, THEREFORE, BE IT ORDAINED, THAT WE, THE MEMBERS OF THE ST. CHARLES PARISH COUNCIL, do hereby approve and authorize the execution of Change Order No. One (1) to the contract for the Ama Pump Station and Force Main Project, to allow the contractor to directional drill portions of the contract at no additional cost or time to the owner.

BE IT FURTHER ORDAINED, that the Parish President is hereby authorized to execute this Change Order to the contract.

vote

The foregoing Ordinance having been submitted to a vote, the vote thereon was as follows:

 

 

 

 

And the ordinance was declared adopted this           day of                                          , 1999, to become effective five (5) days after this publication in the Official Journal.

 

 

 