File #: 2020-0281    Version: 1 Name: Change Order No. 2 (Final) for the Ellington Drainage Pump Station Project No. P080905-5D, Grant Reference Project No. H.013148, as part of the West Bank Hurricane Protection Levee Project
Type: Ordinance Status: Enacted
File created: 9/21/2020 In control: Parish Council
On agenda: 10/5/2020 Final action: 10/5/2020
Enactment date: Enactment #: 20-10-2
Title: An ordinance approving and authorizing the execution of Change Order No. 2 (Final) for the Ellington Drainage Pump Station Project No. P080905-5D, Grant Reference Project No. H.013148, as part of the West Bank Hurricane Protection Levee Project, to decrease the contract amount by $89,182.05 and increase the contract time by thirty (30) days.
Sponsors: Matthew Jewell, Department of Public Works
Indexes: Hurricane Protection Levee (WB - Ellington), Public Works (Dept. of)
Attachments: 1. Change Order No. 2 Final, 2. Ellington Drainage PS - WCD No. 8, 3. Ellington Drainage PS - Ordinance No. 18-11-1, 4. Ellington Drainage PS - Ordinance No. 19-6-3, 5. 2020-0281 Final Ord 20-10-2 with change order
Related files: 2018-0226, 2017-0354, 2018-0292, 2018-0324, 2019-0163, 2022-0356, 2021-0101, 2013-0339, 2022-0063

2020-0281

INTRODUCED BY:                     MATTHEW JEWELL, PARISH PRESIDENT

                                                               (DEPARTMENT OF PUBLIC WORKS)

ORDINANCE NO.  _____________

Title

An ordinance approving and authorizing the execution of Change Order No. 2 (Final) for the Ellington Drainage Pump Station Project No. P080905-5D, Grant Reference Project No. H.013148, as part of the West Bank Hurricane Protection Levee Project, to decrease the contract amount by $89,182.05 and increase the contract time by thirty (30) days.

body

WHEREAS,                     Ordinance No. 18-11-1, adopted November 5, 2018, by the St. Charles Parish Council, approved and authorized the execution of a contract with Sealevel Construction, Inc. for the Ellington Drainage Pump Station Project No. P080905-5D, Grant Reference Project No. H.013148, in the amount of $8,288,890.00; and,

WHEREAS,                     Ordinance No. 19-6-3, adopted June 3, 2019, by the St. Charles Parish Council approved and authorized Change Order No. 1 to the contract with Sealevel Construction Inc. for the Ellington Pump Station Project No. P080905-5D, Grant Reference Project No. H.013148, for an increased amount of $36,252.00, and an increase of contract time by fifty-nine (59) days; and,

WHEREAS,                     Change Order No. 2 (Final) is a result of changes within the scope of the contract to modify quantities to accurately reflect the final balancing of the project line items for the construction amount, and to add a lump sum amount of $9,065.25 for excavation and concrete work necessary for the sheet pile wall intake; and,

WHEREAS,                     the decrease in contract amount by $89,182.05 is a result of a decrease in quantity for five (5) bid line items, an increase in quantity of three (3) line items, the addition of two (2) line items and the deletion of six (6) bid line items; and,

WHEREAS,                     the increase in contract time by thirty (30) days is a result of the added work from Work Change Directive No. 8 (4 days) and the amount of time necessary for SCP to complete the telemetry work (26 days).

THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS,

SECTION I.                     That Change Order No. 2 (Final) for the Ellington Drainage Pump Station Project No. P080905-5D, Grant Reference Project No. H.013148, as part of the West Bank Hurricane Protection Levee Project, to decrease the contract amount by $89,182.05 and increase the contract time of thirty (30) days is hereby approved and accepted.

SECTION II.                     That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.

                     The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:

 

 

 

 

                     And the ordinance was declared adopted this _______ day of ___________, 2020,

to become effective five (5) days after publication in the Official Journal.

 

 

CHAIRMAN:______________________________________________

SECRETARY:_____________________________________________

DLVD/PARISH PRESIDENT:_________________________________

APPROVED:______________ DISAPPROVED:__________________

 

PARISH PRESIDENT:______________________________________

RETD/SECRETARY:_______________________________________

AT:_______________ RECD BY: _____________________________