File #: 1999-4919    Version: 1 Name: Change Order No. Three Wastewater Regionalization Program/Destrehan Regional Wastewater Treatment Plant Contract
Type: Ordinance Status: Enacted
File created: 9/20/1999 In control: Parish Council
On agenda: 10/4/1999 Final action: 10/4/1999
Enactment date: 10/4/1999 Enactment #: 99-10-5
Title: An ordinance to approve and authorize the execution of Change Order No. Three (3) for the St. Charles Parish Wastewater Regionalization Program – Destrehan Regional Wastewater Treatment Plant Contract to decrease the contract amount by $111,308.77.
Sponsors: Chris A. Tregre, Department of Wastewater
Indexes: SPW (Wastewater Regionalization - Destrehan Regional Wastewater Treatment Plant)
Attachments: 1. 1999-4919 Change Order.pdf, 2. 1999-4919 Final Ord 99-10-5 with Change Order
 
INTRODUCED BY:      CHRIS A. TREGRE, PARISH PRESIDENT
                  (DEPARTMENT OF WASTEWATER)
ORDINANCE NO.  ____________
Title
An ordinance to approve and authorize the execution of Change Order No. Three (3) for the St. Charles Parish Wastewater Regionalization Program - Destrehan Regional Wastewater Treatment Plant Contract to decrease the contract amount by $111,308.77.
Body
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I.            That Ordinance No. 97-10-5 adopted October 6, 1997, by the St. Charles Parish Council, approved and authorized the execution of a contract with Roxco, Ltd. for the construction of the St. Charles Parish Wastewater Regionalization Program - Destrehan Regional Wastewater Treatment Plant Project in the amount of $16,986,881.00; and,
SECTION II.            That Ordinance No. 97-11-7 adopted November 17, 1997, by the St. Charles Parish Council, approved and authorized the execution of Change Order No. One (1) for the St. Charles Parish Wastewater Regionalization Program - Destrehan Regional Wastewater Treatment Plant Project to decrease the contract amount by $679,981.00; and,
SECTION III.      That Ordinance No. 99-6-17 adopted June 21, 1999, by the St. Charles Parish Council, approved and authorized the execution of Change Order No. Two (2) for the St. Charles Parish Wastewater Regionalization Program - Destrehan Regional Wastewater Treatment Plant Project to increase the contract time by 28 calendar days; and,
SECTION IV.       That it is necessary to decrease the contract amount by $111,308.77.
NOW, THEREFORE, BE IT ORDAINED, THAT WE, THE MEMBERS OF THE ST. CHARLES PARISH COUNCIL, do hereby approve and authorize the execution of Change Order No. Three (3) to the contract for the St. Charles Parish Wastewater Regionalization Program - Destrehan Regional Wastewater Treatment Plant Project, to decrease the contract amount by $111,308.77; and,
BE IT FURTHER ORDAINED, that the Parish President is hereby authorized to execute this Change Order to the contract.
Vote
The foregoing Ordinance having been submitted to a vote, the vote thereon was as follows:
DestrehanWWTP.CO3.ORD
 
 
 
 
And the ordinance was declared adopted this  ___  day of                          , 1999, to become effective five (5) days after this publication in the Official Journal.
 
 
 
CHAIRMAN: _______________________________________
SECRETARY: ______________________________________
DLVD/PARISH PRESIDENT: __________________________
APPROVED:                      DISAPPROVED: ______________
 
 
PARISH PRESIDENT: _______________________________
RETD/SECRETARY: ________________________________
AT:                               RECD BY: _______________________