Title: An ordinance to approve and authorize the execution of Change Orders No. 1 and 2 (Final) for the St. Charles Parish Emergency Operations Center, FEMA Project No. 2008-EO-T8-0010, FP&C Project No. 50-J45-09-01, to decrease the contract amount by $165,477.71 and increase the contract time by two-hundred thirty-nine (239) days.
Sponsors: V.J. St. Pierre Jr., Department of Emergency Preparedness
Indexes: Em. Prep. (Dept. of)
Attachments: 1. NE Change Order No-2.pdf, 2. Executed Change Order - 1 cover.pdf, 3. 2013-0481 Change Orders-F, 4. 2013-0481 Final Ord 14-1-9 with Change Order
Related files: 2012-0394, 2011-0374, 2011-0309, 2009-0442, 2010-0299, 2009-0363, 2010-0098, 2013-0085, 2013-0198, 2013-0183, 2015-0316, 2013-0482, 2019-0269, 2019-0296, 2015-0050, 2016-0182, 2016-0275
2013-0481
INTRODUCED BY:      V.J. ST. PIERRE, JR., PARISH PRESIDENT
                  (DEPARTMENT OF EMERGENCY PREPAREDNESS)
ORDINANCE NO.                   
Title
An ordinance to approve and authorize the execution of Change Orders No. 1 and 2 (Final) for the St. Charles Parish Emergency Operations Center, FEMA Project No. 2008-EO-T8-0010, FP&C Project No. 50-J45-09-01, to decrease the contract amount by $165,477.71 and increase the contract time by two-hundred thirty-nine (239) days.
Body
WHEREAS,      Ordinance No. 11-12-3, adopted December 5, 2011, by the St. Charles Parish Council, approved and authorized the execution of a contract with Aegis Construction, Inc, for the construction of the St. Charles Parish Emergency Operations Center in the amount of $5,845,000.00; and,
WHEREAS,      the decrease in contract amount from Change Orders No. 1 and 2 (Final) is a result of a combination of a change directives and sales tax credit; and,
WHEREAS,      the increase in contract time of two-hundred thirty-nine (239) days is related to change directives.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I.      That Change Orders No. 1 and 2 (Final) for the St. Charles Parish Emergency Operations Center, FEMA Project No. 2008-EO-T8-0010, FP&C Project No. 50-J45-09-01, to decrease the contract amount by $165,477.71 and increase the contract time by two-hundred thirty-nine (239) days, is hereby approved and accepted.
SECTION II.      That the Parish President is hereby authorized to execute said Change Orders on behalf of St. Charles Parish.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
 
 
 
 
And the ordinance was declared adopted this            day of                       , 2014, to become effective five (5) days after publication in the Official Journal.
 
 
 
CHAIRMAN:                                     
SECRETARY:                                     
DLVD/PARISH PRESIDENT:                         
APPROVED:                         DISAPPROVED:             
 
PARISH PRESIDENT:                               
RETD/SECRETARY:                               
AT:                              RECD BY: