logo  ST. CHARLES PARISH, LA
File #: 2003-0334    Version: 1 Name: C. O. 1 - Final for Parish Project No. P011003, Willowdale Canal Erosion Control, to balance contractual quantities with actual job quantities
Type: Ordinance Status: Enacted
File created: 9/22/2003 In control: Parish Council
On agenda: Final action: 10/6/2003
Enactment date: 10/6/2003 Enactment #: 03-10-5
Title: An ordinance approving and authorizing the execution of Change Order No. One (1) - Final for Parish Project No. P011003, Willowdale Canal Erosion Control, to balance contractual quantities with actual job quantities.
Sponsors: Albert D. Laque, Department of Public Works
Indexes: DRO (Willowdale Canal Erosion Control)
Attachments: 1. 2003-0334 Change Order, 2. 2003-0334 Final Ord 03-10-5 with Change Order
Related files: 2003-0116
2003-0334
INTRODUCED BY:      ALBERT D. LAQUE, PARISH PRESIDENT
                  (DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO. _____      
Title
An ordinance approving and authorizing the execution of Change Order No. One (1) - Final for Parish Project No. P011003, Willowdale Canal Erosion Control, to balance contractual quantities with actual job quantities.
Body
WHEREAS,      Ordinance No. 03-4-14, adopted April 21, 2003 by the St. Charles Parish Council awarded construction of Parish Project No. P011003, Willowdale Canal Erosion Control, to Civil Construction Contractors, Inc. for the amount of $131,212.94; and,
WHEREAS,      the project was completed by Civil Construction Contractors, Inc. $1114.46 under the original Contract Price of $131,212.94; and,
WHEREAS,      the project was completed by Civil Construction Contractors, Inc. eleven (11) days after the original completion date of September 13, 2003 due to inclimate weather and the addition of one yard to be graded and sodded; and,
WHEREAS,      Change Order No. One (1) - Final is necessary to close out the construction contract with Civil Construction Contractors, Inc. for Parish Project No. P011003, Willowdale Canal Erosion Control.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I.      That Change Order No. One (1) - Final to the contract for Parish Project No. 011003, Willowdale Canal Erosion Control, to offer a contract amount credit of $1114.46 and an increase in contract time of eleven (11) days to St. Charles Parish is hereby approved.
SECTION II.      That the Parish President is hereby authorized to execute said Change Order.
Vote
      The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
 
 
 
 
      And the ordinance was declared adopted this _____ day of ____________, 2003, to become effective five (5) days after publication in the Official Journal.
 
 
 
 
CHAIRMAN:______________________________________________
SECRETARY:_____________________________________________
DLVD/PARISH PRESIDENT:_________________________________
APPROVED:______________ DISAPPROVED:__________________
 
PARISH PRESIDENT:______________________________________
RETD/SECRETARY:_______________________________________
AT:_______________ RECD BY: _____________________________