logo  ST. CHARLES PARISH, LA
File #: 2021-0164    Version: 1 Name: C.O. No. 1 (Final) - SC West Bank River Intake Modification Project No. WWKS 98
Type: Ordinance Status: Enacted
File created: 6/7/2021 In control: Parish Council
On agenda: 6/21/2021 Final action: 6/21/2021
Enactment date: Enactment #: 21-6-15
Title: An ordinance approving and authorizing the execution of Change Order No. 1 (Final) for the St. Charles West Bank River Intake Modification Project No. WWKS 98 to increase the contract amount by $63,750.00, and to decrease the contract time by twenty (20) days.
Sponsors: Matthew Jewell, Department of Waterworks
Indexes: WW (WB River Intake Modifications)
Attachments: 1. 2021-0164 West Bank River Intake Modification, WWKS 98, Change Order, 042221.pdf, 2. 2021-0164 Final Ord 21-6-15 with change order
Related files: 2018-0149, 2020-0110

2021-0164

INTRODUCED BY:                     MATTHEW JEWELL, PARISH PRESIDENT

                     (DEPARTMENT OF WATERWORKS)

ORDINANCE NO.                                                                 

Title

An ordinance approving and authorizing the execution of Change Order No. 1 (Final) for the St. Charles West Bank River Intake Modification Project No. WWKS 98 to increase the contract amount by $63,750.00, and to decrease the contract time by twenty (20) days.

Body

WHEREAS,                     Ordinance No. 20-5-6 adopted May 04, 2020 by the St. Charles Parish Council, approved and authorized the execution of a contract with Deep South Construction & Salvage, LLC for the St. Charles West Bank River Intake Modification Project No. WWKS 98 in the amount of $589,265.00; and,

WHEREAS,                     Change Order No.1 (and final) is a result of changes within the contract to add work items within the existing contract unit prices, removal of unforeseen obstructions to evaluate intake piping integrity, cutting existing pipes for reworking of three (3) 20” dia. intakes and additional installation of 22.5 degree fittings for a 21’4” channel-ward pipe extension into the Mississippi River; and,

WHEREAS,                     the increase in contract amount by $63,750.00 is a result of final quantity adjustments and the unforeseen additional items described herein; and,

WHEREAS,                     the decrease in contract time by twenty (20) calendar days is a result of Deep South’s decision to work overtime (at no additional cost to St. Charles Parish), for the duration of the project, in order to minimize disruption of construction activities during the peak of hurricane season.

THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:

SECTION I.                     That Change Order No. 1 (Final) for the St. Charles West Bank River Intake Modification Project No. WWKS 98 to increase the contract amount by $63,750.00, and to decrease the contract time by twenty (20) days is hereby approved and accepted.

SECTION II.                     That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.

The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:

 

 

 

 

                     And the ordinance was declared adopted this _______ day of ___________, 2021 to become effective five (5) days after publication in the Official Journal.

 

 

CHAIRMAN: ______________________________________________

SECRETARY: _____________________________________________

DLVD/PARISH PRESIDENT: _________________________________

APPROVED: ______________ DISAPPROVED: __________________

 

PARISH PRESIDENT: ______________________________________

RETD/SECRETARY: _______________________________________

AT: _______________ RECD BY: _____________________________