logo  ST. CHARLES PARISH, LA
File #: 2024-0320    Version: 1 Name: C.O. No. 2 for the Destrehan Pump Station (P.S.) No. 2 Conveyance Improvements, (Project No. P181101), to decrease the contract amount by $45,522.00 and increase the contract time by 82 calendar days
Type: Ordinance Status: Enacted
File created: 9/23/2024 In control: Parish Council
On agenda: 10/7/2024 Final action: 10/7/2024
Enactment date: Enactment #: 24-10-2
Title: An ordinance approving and authorizing the execution of Change Order No. 2 for the Destrehan Pump Station (P.S.) No. 2 Conveyance Improvements, (Project No. P181101), to decrease the contract amount by $45,522.00 and increase the contract time by 82 calendar days.
Sponsors: Matthew Jewell, Department of Public Works
Indexes: DRO (Canal Imp. Near Destrehan Pump Station No. 2), Public Works (Dept. of)
Attachments: 1. 2024-0320 P181101 Change Order #2 Partially Executed, 2. 2024-0320 Final Ord 24-10-2 with change order, 3. 2024-0320 Recordation Documents
Related files: 2024-0119, 2020-0200, 2019-0193, 2023-0157, 2023-0141, 2023-0143, 2025-0026

2024-0320

INTRODUCED BY:                     MATTHEW JEWELL, PARISH PRESIDENT

(DEPARTMENT OF PUBLIC WORKS)

ORDINANCE NO.  ___________

Title

An ordinance approving and authorizing the execution of Change Order No. 2 for the Destrehan Pump Station (P.S.) No. 2 Conveyance Improvements, (Project No. P181101), to decrease the contract amount by $45,522.00 and increase the contract time by 82 calendar days.

Body

WHEREAS,                     Ordinance No. 19-7-3 adopted July 1, 2019, by the St. Charles Parish Council, approved and authorized the execution of a professional service multi-phase project agreement with Picciola & Associates, Inc., for providing all necessary professional engineering services for a project that increases the trash screen capacity and the size of the sump into Destrehan Pump Station (P.S.) No. 2 (Parish Project Number P181101), in the amount not to exceed $183,375.00; and,

WHEREAS,                     Ordinance No. 20-7-13 adopted July 27, 2020, by the St. Charles Parish Council, approved and authorized the execution of Amendment No. 1 to Ordinance No. 19-7-3 which approved the Professional Services Agreement with Picciola & Associates, Inc., for providing necessary professional engineering services for a project that improves the hydraulic capacity into Destrehan Pump Station (P.S.) No. 2 (Parish Project Number P181101), in the amount not to exceed $54,927.00, increasing the overall not to exceed amount to $238,302.00; and,

WHEREAS,                     Ordinance No. 23-6-10 adopted June 19, 2023, by the St. Charles Parish Council, approved and authorized the execution of a Contract with Sealevel Construction, Inc., for the Destrehan Pump Station (P.S.) No. 2 Conveyance Improvements (Project No. P181101), in the amount of $9,190,697.00; and,

WHEREAS,                     Ordinance No. 23-6-12 adopted June 19, 2023, by the St. Charles Parish Council, approved and authorized a Professional Services Agreement with Alpha Testing and Inspection, Inc., to perform testing services for Destrehan Pump Station (P.S.) No. 2 Conveyance Improvements (Project No. P181101), in the not to exceed amount of $66,000.00; and,

WHEREAS,                     Ordinance No. 23-7-5 adopted July 10, 2023, by the St. Charles Parish Council, approved and authorized the execution of Amendment No. 2 to Ordinance No. 19-7-3 which approved the Professional Services Agreement with Picciola & Associates, Inc., to perform engineering services for the Destrehan Pump Station (P.S.) No. 2 Conveyance Improvements (Project No. P181101), in the not to exceed amount of $111,500.00, increasing the overall not to exceed amount to $349,802.00; and,

WHEREAS,                     Ordinance No. 24-4-4 adopted April 1, 2024, by the St. Charles Parish Council, approved and authorized the execution of Change Order No. 1 for the Destrehan Pump Station (P.S.) No. 2 Conveyance Improvements, (Project No. P181101), to increase the contract amount by $66,500.00 and increase contract time by eight (8) calendar days; and,

WHEREAS,                     it is necessary to amend the construction contract with Sealevel Construction, Inc. again, to revise contract items for concrete and deformed reinforcing steel and add a new contract item for structural metal work due to a field change to modify the trash rake structure, to remove the contract items for fencing and cable articulated concrete bock mattress, and add contract items for repairs to scour areas and bulkhead cap and embankment, resulting in a decrease to the contract amount by $45,522.00 and an increase to the contract time by 82 calendar days.

THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:

SECTION I.                     That Change Order No. 2 for Destrehan Pump Station (P.S.) No. 2 Conveyance Improvements, (Project No. P181101), to decrease the contract amount by $45,522.00 and increase the contract time by 82 calendar days is hereby approved and accepted.

SECTION II.                     That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.

                     The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:

 

 

 

 

And the ordinance was declared adopted this ______ day of __________, 2024, to become effective five (5) days after this publication in the official journal.

 

 

CHAIRMAN:                                                                                                                               

SECRETARY:                                                                                                                               

DLVD/PARISH PRESIDENT:                                                                                     

APPROVED:                       DISAPPROVED:                                                                

 

PARISH PRESIDENT:                                                                                                          

RETD/SECRETARY:                                                                                                           

AT:                        RECD BY: