logo  ST. CHARLES PARISH, LA
File #: 2025-0104    Version: 1 Name: C.O. No. 3 with Kass Bros., Inc., for Concrete Maintenance 2023-24 (Project No. P230803), to increase the contract amount by $288,798.91 and increase the contract time by twenty-four (24) days
Type: Ordinance Status: Public Hearing
File created: 4/7/2025 In control: Parish Council
On agenda: 4/21/2025 Final action:
Enactment date: Enactment #:
Title: An ordinance approving and authorizing the execution of Change Order No. 3 with Kass Bros., Inc., for Concrete Maintenance 2023-24 (Project No. P230803), to increase the contract amount by $288,798.91 and increase the contract time by twenty-four (24) days.
Sponsors: Matthew Jewell, Department of Public Works
Attachments: 1. 2025-0104 CO 3 Partially Executed
Related files: 2025-0001, 2024-0204, 2022-0180, 2023-0250, 2024-0246, 2024-0383, 2024-0422

2025-0104

INTRODUCED BY:                     MATTHEW JEWELL, PARISH PRESIDENT

                                                               (DEPARTMENT OF Public Works)

ORDINANCE NO.  ___________

Title

An ordinance approving and authorizing the execution of Change Order No. 3 with Kass Bros., Inc., for Concrete Maintenance 2023-24 (Project No. P230803), to increase the contract amount by $288,798.91 and increase the contract time by twenty-four (24) days.

Body

WHEREAS,                     Ordinance No. 22-7-2 adopted on July 5, 2022, by the St. Charles Parish Council, approved and authorized the execution of a Professional Services Agreement with Digital Engineering & Imaging, Inc., to perform planning services for the Road Maintenance 2022-23 (Project No. P220501), in the not to exceed amount of $316,728.72; and,

WHEREAS,                     Ordinance No. 23-9-2 adopted on September 25, 2023, by the St. Charles Parish Council, approved and authorized  the execution of Amendment No. 1 to Ordinance No. 22-7-2, which approved the Professional Services Agreement with Digital Engineering & Imaging, Inc. to perform planning services for the Road Maintenance 2022-23 (Project No. P220501), adding Concrete Maintenance 2023-24 (Project No. P230803), in the amount of $211,740.00; and,

WHEREAS,                     Ordinance 24-6-16 adopted on June 17, 2024, by the St. Charles Parish Council, approved and authorized the execution of Amendment No. 2 to Ordinance No. 22-7-2 which approved the Professional Services Agreement with Digital Engineering & Imaging, Inc., to perform planning services for the Road Maintenance 2022-23 (Project No. P220501), in the amount of $135,238.00; and,

WHEREAS,                     Ordinance No. 24-7-19 adopted on July 22, 2024, by the St. Charles Parish Council, approved and authorized the execution of a Contract with Kass Bros., Inc., for Concrete Maintenance 2023-24 (Project No. P230803), in the amount of $914,593.10; and,

WHEREAS,                     Ordinance No. 24-12-4 adopted on December 2, 2024, by the St. Charles Parish Council, approved and authorized the execution of Change Order No. 1 with Kass Bros., Inc., for Concrete Maintenance 2023-24 (Project No. P230803), to increase the contract amount by $193,430.85 and increase the contract time by thirty-five (35) days; and,

WHEREAS,                     Ordinance No. 25-1-3 adopted on January 6, 2025, by the St. Charles Parish Council, approved and authorized the execution of Change Order No. 2 with Kass Bros., Inc., for Concrete Maintenance 2023-24 (Project No. P230803), to increase the contract amount by $328,314.80 and to increase the contract time by sixty (60) days; and,

WHEREAS,                     Ordinance No. 25-1-6 adopted on January 27, 2025, by the St. Charles Parish Council, approved and authorized the execution of Amendment No. 3 to Ordinance No. 22-7-2, which approved the Professional Services Agreement with Digital Engineering & Imaging, Inc., to perform planning services for Road Maintenance 2022-23 (Project No. P220501), in the amount of $90,086.00; and,

WHEREAS,                     it is necessary to amend the construction contract for Concrete Maintenance 2023-24 (Project No. P230803), to incorporate items added during construction that improved the quality of the roadways already being improved; and,

WHEREAS,                     St. Charles Parish and Kass Bros., Inc., have mutually agreed to increase the contract price by $288,798.91, bringing the total construction cost to $1,725,137.66 and add twenty-four (24) calendar days to complete the work.

THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:

SECTION I.                     That Change Order No. 3 for Concrete Maintenance 2023-24 (Project No. P230803), to increase the construction contract amount by $288,798.91, bringing the total construction cost to $1,725,137.66, and to increase the contract time by twenty-four (24) calendar days is hereby approved and accepted.

SECTION II.                     That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.

 

 

The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:

 

 

 

 

And the ordinance was declared adopted this ______ day of ____________, 2025, to become effective five (5) days after publication in the Official Journal.

 

 

CHAIRMAN:                                                                                                                               

SECRETARY:                                                                                                                               

DLVD/PARISH PRESIDENT:                                                                                     

APPROVED :                       DISAPPROVED:                                           

 

PARISH PRESIDENT:                                                                                                          

RETD/SECRETARY:                                                                                                           

AT:                        RECD BY: