File #: 2025-0270    Version: 1 Name: Amendment No. 2 to Ordinance No. 21-8-16, which approved the PSA with Duplantis Design Group (DDG), to perform additional engineering services for the Des Allemands Boat Launch (Project No. P210705)
Type: Ordinance Status: Enacted
File created: 9/8/2025 In control: Parish Council
On agenda: 9/22/2025 Final action: 9/22/2025
Enactment date: Enactment #: 25-9-7
Title: An ordinance approving and authorizing the execution of Amendment No. 2 to Ordinance No. 21-8-16, which approved the Professional Services Agreement with Duplantis Design Group (DDG), to perform additional engineering services for the Des Allemands Boat Launch (Project No. P210705), to include construction administration and inspection for the construction of the actual Boat Launch, increasing the contract by $394,440.19, for an overall value of $1,004,796.19.
Sponsors: Matthew Jewell, Department of Public Works
Attachments: 1. 2025-0270 Duplantis Design Group - Amendment - September 02, 2025, 2. 2025-0270 Duplantis Design Group - Rate Sheet - September 02, 2025, 3. 2025-0270 Duplantis Design Group - Corporate Resolution - September 02, 2025, 4. 2025-0270 Final Ord. 25-9-7 with Agreement, 5. 2025-0270 Correspondence 09.29.2025
Related files: 2024-0329, 2023-0179, 2021-0077, 2021-0222, 2025-0308

2025-0270

INTRODUCED BY:                     MATTHEW JEWELL, PARISH PRESIDENT

(DEPARTMENT OF Public Works)

ORDINANCE NO:  ___________

Title

An ordinance approving and authorizing the execution of Amendment No. 2 to Ordinance No. 21-8-16, which approved the Professional Services Agreement with Duplantis Design Group (DDG), to perform additional engineering services for the Des Allemands Boat Launch (Project No. P210705), to include construction administration and inspection for the construction of the actual Boat Launch, increasing the contract by $394,440.19, for an overall value of $1,004,796.19.

Body

WHEREAS,                     Ordinance No. 21-4-2 adopted on April 5, 2021, by the St. Charles Parish Council, approved and authorized the execution of an Act of Donation by and between Chevron U.S.A. Inc. and St. Charles Parish for certain parcel of land comprising of approximately 109.8 acres for the purpose of a boat launch and park along Bayou Des Allemands; and,

WHEREAS,                     Ordinance No. 21-8-16 adopted on August 23, 2021, by the St. Charles Parish Council, approved and authorized the execution of a Professional Services Agreement with Duplantis Design Group (DDG), to perform engineering services for a Des Allemands Boat Launch (Project No. P210705); and,

WHEREAS,                     Ordinance No. 23-7-16 adopted on July 31, 2023, by the St. Charles Parish Council, approved and authorized the execution of a Cooperative Endeavor Agreement between St. Charles Parish and the Lafourche Basin Levee District relative to a levee lift for the Sunset Drainage District within the West Bank Hurricane Protection Levee System (Project A) and access roadway and surcharge area for a future boat ramp located on property known as Des Allemands Boat Launch (Project B); and,

WHEREAS,                     Ordinance No. 24-10-3 on October 21, 2024, by the St. Charles Parish Council, approved and authorized the execution of an Amendment No. 1 to Ordinance No. 21-8-16, which approved the Professional Services Agreement with Duplantis Design Group (DDG), to perform engineering services for the Des Allemands Boat Launch (Project No. P210705), to reallocate funds for the current and future boat launch project phases, resulting in no increase in contract price or time; and,

WHEREAS,                     the Des Allemands Boat Launch plans and specifications have been completed by Duplantis Design Group (DDG) and St. Charles Parish is ready to bid the project, therefore funds for Construction Administration and Resident Project Representative (RPR) need to be added to the contract; and,

WHEREAS,                     St. Charles Parish and Duplantis Design Group (DDG) have mutually agreed on a not to exceed price of $394,440.19 to complete the work, increasing the overall contract value to $1,004,796.19, as described in Amendment No. 2.

THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:

SECTION I.                     That Amendment No. 2 to the Professional Services Agreement between St. Charles Parish and Duplantis Design Group (DDG), for the Des Allemands Boat Launch (Project No. P210705), to increase the contract by $394,440.19 for an overall value of $1,004,796.19, is hereby approved and accepted.

SECTION II.                     That the Parish President is hereby authorized to execute said Amendment on behalf of St. Charles Parish.

The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:

 

 

 

 

And the ordinance was declared adopted this _______ day of ___________, 2025, to become effective five (5) days after publication in the Official Journal.

 

 

CHAIRMAN:                                                                                                          

SECRETARY:                                                                                     

DLVD/PARISH PRESIDENT:                                                                

APPROVED :                       DISAPPROVED:                      

 

PARISH PRESIDENT:                                                                                     

RETD/SECRETARY:                                                                                      

AT:                        RECD BY: