Title: An ordinance approving and authorizing the execution of Change Order No. 2 (Final) for Parish Project No. S100901 Thoroughbred Lift Station No. 5931 Renovations and 8-Inch Force Main Addition to increase the contract time by 111 days.
Sponsors: V.J. St. Pierre Jr., Department of Wastewater
Indexes: SPW (Thoroughbred Lift Station #5931 Imp.)
Attachments: 1. Change order.doc, 2. 2012-0077 Change Order-F, 3. 2012-0077 Final Ord 12-2-6 with Change Order
Related files: 2011-0052, 2011-0376
2012-0077
INTRODUCED BY:       V.J. ST. PIERRE, JR., PARISH PRESIDENT
                   (DEPARTMENT OF WASTEWATER)
ORDINANCE NO.  _____            
Title
An ordinance approving and authorizing the execution of Change Order No. 2 (Final) for Parish Project No. S100901 Thoroughbred Lift Station No. 5931 Renovations and 8-Inch Force Main Addition to increase the contract time by 111 days.
Body
WHEREAS,      Ordinance No. 11-2-9, adopted February 21, 2011, by the St. Charles Parish Council approved and authorized the execution of a contract with Sealevel Construction, Inc. for Parish Project No. S100901 Thoroughbred Lift Station No. 5931 Renovations and 8-Inch Force Main Addition in the amount of $159,000.00; and, Ordinance No. 11-12-4 adopted December 5, 2011 by the St. Charles Parish Council, approved and authorized the execution of Change Order No. 1 increasing the contact amount by $1,100.00 to $160,100.00, and,
WHEREAS,      The increase in contract time resulted from the water level of the Mississippi River rising above 11+00 MSL prohibited work for 111 days at which time the water level of the Mississippi River dropped below 11+00 MSL and work was allowed to resume.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS,
SECTION I.      That Change Order No. 2(Final) for Parish Project No. S100901 Thoroughbred Lift Station No. 5931 Renovations and 8-Inch Force Main Addition to increase the contract time by 111 days is hereby approved and accepted.
SECTION II.      That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.
Vote
      The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
 
 
 
 
      And the ordinance was declared adopted this _____ day of ___________, 2011,
to become effective five (5) days after publication in the Official Journal.
 
 
 
CHAIRMAN:_________________________________________
SECRETARY:________________________________________
DLVD/PARISH PRESIDENT:____________________________
APPROVED:______________ DISAPPROVED:_____________
 
PARISH PRESIDENT:_________________________________
RETD/SECRETARY:__________________________________
AT:_______________ RECD BY: ________________________