File #: 2012-0418    Version: 1 Name: Contract with Advanced Quality Construction, Inc. for Dunleith Canal Stabilization Ph 3
Type: Ordinance Status: Enacted
File created: 11/19/2012 In control: Parish Council
On agenda: Final action: 12/3/2012
Enactment date: 12/3/2012 Enactment #: 12-12-6 AMENDED
Title: An ordinance to approve and authorize the execution of a contract with Advanced Quality Construction, Inc. for project P081102-4 Dunleith Canal Stabilization Ph3 in the amount of $1,018,626.82.
Sponsors: V.J. St. Pierre Jr., Department of Public Works, Wendy Benedetto
Indexes: DRO (Dunleith Canal Stab., Ph. 3)
Attachments: 1. Cover Memo for Introduce Ordinance for Construction Contract, 2. 2012-0418 Contract-F, 3. 2012-0418 Final Ord 12-12-6 with Contract
Related files: 2015-0049, 2013-0211, 2000-0505, 2002-0396, 2003-0199, 2011-0021, 2001-0219, 2003-0025, 2008-0481, 2010-0277, 2011-0296, 2012-0211, 2014-0348, 2014-0402, 2015-0339, 2018-0066, 2017-0216, 2020-0101, 2015-0150, 2015-0241, 2015-0311, 2016-0247, 2016-0299, 2019-0265, 2019-0347, 2020-0313
2012-0418
INTRODUCED BY:      V.J. ST. PIERRE, JR., PARISH PRESIDENT
                  (DEPARTMENT OF PUBLIC WORKS)
                  WENDY BENEDETTO, COUNCILWOMAN, DISTRICT III
ORDINANCE NO.  __________
Title
An ordinance to approve and authorize the execution of a contract with Advanced Quality Construction, Inc. for project P081102-4 Dunleith Canal Stabilization Ph3 in the amount of $1,018,626.82.
Body
WHEREAS,      sealed bids were received by St. Charles Parish on October 30, 2012 for project P081102-4 Dunleith Canal Stabilization Ph3; and,
WHEREAS,      Evans-Graves Engineers, Inc., the Engineer for the Project, has reviewed the bids and recommend that the Contract be awarded to the low bidder, Advanced Quality Construction, Inc. in the amount of $1,018,626.82 to include base bid plus alternates 1 and 2; and,
WHEREAS,      installation of this project will install vinyl sheet piling to stabilize the canal bank on the resident's side of the Dunleith Canal continuing from the end of phase 2 north for a distance of 960 ft.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
      SECTION I.      That the bid of Advanced Quality Construction, Inc., for the construction of project P081102-4 Dunleith Canal Stabilization Ph3, be hereby approved and accepted, in the amount of $1,018,626.82.
      SECTION II.      That the Parish President is hereby authorized to execute the attached contract documents on behalf of St. Charles Parish.
Vote
      The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
 
 
 
 
      And the ordinance was declared adopted this ______ day of __________, 2012,
to become effective five (5) days after publication in the Official Journal.
 
 
 
CHAIRMAN:______________________________________________
SECRETARY:_____________________________________________
DLVD/PARISH PRESIDENT:_________________________________
APPROVED:______________ DISAPPROVED:__________________
 
PARISH PRESIDENT:______________________________________
RETD/SECRETARY:_______________________________________
AT:_______________RECD BY: _____________________________