File #: 2016-0247    Version: 1 Name: Change Order No. 1 (Final) for Dunleith Canal Stabilization Phase 5
Type: Ordinance Status: Enacted
File created: 6/20/2016 In control: Parish Council
On agenda: 7/5/2016 Final action: 7/5/2016
Enactment date: Enactment #: 16-7-3
Title: An ordinance approving and authorizing the execution of Change Order No. 1 (Final) for Parish Project No P081102-6, Dunleith Canal Stabilization Phase 5, to balance the contract quantities with actual quantities resulting in an increase of $8,907.00 and decrease in contract time of 16 days.
Sponsors: Lawrence 'Larry' Cochran, Department of Public Works
Indexes: DRO (Dunleith Canal Stab., Ph. 5)
Attachments: 1. 2016-0247 Dunleith Phase 5 CO #1, 2. 2016-0247 Change Order-F, 3. 2016-0247 Final Ord 16-7-3 with Change Order
Related files: 2015-0311, 2015-0241, 2013-0211, 2014-0402, 2015-0049, 2015-0150, 2003-0025, 2003-0199, 2010-0277, 2011-0021, 2011-0296, 2012-0211, 2012-0418, 2014-0348, 2000-0505, 2001-0219, 2002-0396, 2008-0481, 2015-0339, 2017-0216, 2020-0101, 2018-0066, 2019-0265, 2019-0347, 2020-0313, 2016-0299

2016-0247

INTRODUCED BY:                     LARRY COCHRAN, PARISH PRESIDENT

                                                               (DEPARTMENT OF PUBLIC WORKS)

ORDINANCE NO.                                                                

Title

An ordinance approving and authorizing the execution of Change Order No. 1 (Final) for Parish Project No P081102-6, Dunleith Canal Stabilization Phase 5, to balance the contract quantities with actual quantities resulting in an increase of $8,907.00 and decrease in contract time of 16 days.

Body

WHEREAS,                     Ordinance No. 15-10-01 adopted October 5, 2015 by the St. Charles Parish Council awarded construction of Parish Project No P081102-6, Dunleith Canal Stabilization Phase 5, to Volute, Inc. in the amount of $1,038,206.00; and,

WHEREAS,                     it is necessary to amend the contract resulting in an increase to the contract amount by $8,907.00 and decrease contract time by 16 days.  Final contract amount will be $1,047,113.00.

THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:

                     SECTION I.                     That Change Order No. 1 (Final) for Parish Project No. P081102-6, Dunleith Canal Stabilization Phase 5, to increase the contract amount by $8,907.00 and decrease the contract time by 16 days is hereby approved and accepted.

                     SECTION II.                     That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.

                     The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:

 

 

 

 

                     And the ordinance was declared adopted this ______ day of __________, 2016, to become effective five (5) days after this publication in the official journal.

 

 