File #: 2019-0217    Version: 1 Name: C.O. No. 1-Parish Project No. S170701 Hahnville Wastewater Treatment Plant (UV Upgrade) to increase the contract amount by $18,950.00 and increase the number of days by 16
Type: Ordinance Status: Enacted
File created: 7/22/2019 In control: Parish Council
On agenda: 8/5/2019 Final action: 8/5/2019
Enactment date: Enactment #: 19-8-2
Title: An ordinance approving and authorizing the execution of Change Order No. 1 for Parish Project No. S170701 Hahnville Wastewater Treatment Plant (UV Upgrade) to increase the contract amount by $18,950.00 and increase the number of days by 16.
Sponsors: Lawrence 'Larry' Cochran, Department of Public Works
Indexes: SPW (Hahnville Wastewater Plant UV Upgrades)
Attachments: 1. 2019-0217 Change Order No. 1 Hahnville WW Treatment Plant - .pdf, 2. 2019-0217 Final Ord 19-8-2 with change order
Related files: 2008-0080, 2007-0057, 2002-0339, 2003-0300, 2004-0359, 2006-0049, 1999-4899, 2000-0434, 2001-0320, 2009-0025, 2010-0081, 2011-0069, 2012-0104, 2013-0072, 2014-0066, 2015-0044, 2016-0128, 2017-0019, 2017-0246, 2018-0012, 2018-0236, 2018-0350, 2019-0409

2019-0217

INTRODUCED BY:                     LARRY COCHRAN, PARISH PRESIDENT

                                                               (DEPARTMENT OF PUBLIC WORKS)

ORDINANCE NO.  _____________

Title

An ordinance approving and authorizing the execution of Change Order No. 1 for Parish Project No. S170701 Hahnville Wastewater Treatment Plant (UV Upgrade) to increase the contract amount by $18,950.00 and increase the number of days by 16.

Body

WHEREAS,                     Ordinance No. 18-9-4 adopted September 17, 2018 by the St. Charles Parish Council awarded construction of Parish Project No. S170701 Hahnville Wastewater Treatment Plant (UV Upgrade) to BLD Services, LLC; and,

WHEREAS,                     it is necessary to amend the contract to adjust the contract quantities with actual quantities resulting in an increase to the contract amount by $18,950.00 and increase the number of days by 16.

THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:

                     SECTION I.                     That Change Order No. 1 for Parish Project No. S170701 Hahnville Wastewater Treatment Plant (UV Upgrade) to increase the contract amount by $18,950.00 and increase the number of days by 16 is hereby approved and accepted.

                     SECTION II.                     That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.

SECTION III.                     St Charles Parish considers the project complete and hereby accepts all improvements.

The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:

 

 

 

 

And the ordinance was declared adopted this               day of                     , 2019, to become effective five (5) days after publication in the Official Journal.

 

 

CHAIRMAN:__________________________________________

SECRETARY:_________________________________________

DLVD/PARISH PRESIDENT:_____________________________

APPROVED:______________ DISAPPROVED:______________

 

PARISH PRESIDENT:__________________________________

RETD/SECRETARY:___________________________________

AT:_______________ RECD BY: _________________________