2015-0364
INTRODUCED BY: V.J. St. Pierre, JR., PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO.
Title
An ordinance approving and authorizing the execution of Change Order No. 1 for Parish Project No P120801, Randolph Pump Station Improvements, to increase the contract amount by $73,305.50 and contract time by 14 days.
Body
WHEREAS, Ordinance No. 15-4-9 adopted April 6, 2015 by the St. Charles Parish Council awarded construction of Parish Project No P120801, Randolph Pump Station Improvements, to Sealevel Construction, Inc. in the amount of $770,450.00; and,
WHEREAS, the cost increase is required to install an additional foundation, additional sheetpile struts, and move the screen bridge 5ft further away from the pump station; and
WHEREAS, the additional time is needed to install these additions
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That Change Order No. 1 for Parish Project No. P120801, Randolph Pump Station Improvements, to increase the contract amount by $73,305.50 and increase the contract time by 14 days is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this ______ day of __________, 2015, to become effective five (5) days after this publication in the official journal.
CHAIRMAN:
SECRETARY:
DLVD/PARISH PRESIDENT:
APPROVED: DISAPPROVED:
PARISH PRESIDENT:
RETD/SECRETARY:
AT: RECD BY: