logo  ST. CHARLES PARISH, LA
File #: 2016-0387    Version: 1 Name: Change Order No. 2 - Willowridge Pump Station, Willowridge Levee - Phase II, as part of the West Bank Hurricane Protection Levee Project
Type: Ordinance Status: Enacted
File created: 11/14/2016 In control: Parish Council
On agenda: 11/28/2016 Final action: 11/28/2016
Enactment date: Enactment #: 16-11-7
Title: An ordinance approving and authorizing the execution of Change Order No. 2 for the Willowridge Pump Station Project No. P080905-4A, Willowridge Levee - Phase II, State Project No.H.010102, as part of the West Bank Hurricane Protection Levee Project, to increase the contract amount by $32,895.00 and increase the contract time by fourteen (14) days.
Sponsors: Lawrence 'Larry' Cochran, Department of Public Works
Indexes: Floods, Highway Dept., Hurricane Protection Levee (WB - Willowridge, Ph. II)
Attachments: 1. 20163-0387 Willowridge PS Change Order No. 2, 2. 2016-0387 Extra Info, 3. 2016-0387 Change Order-F, 4. 2016-0387 Final Ord 16-11-7 with Change Order
Related files: 2017-0411, 2017-0350, 2011-0307, 2012-0294, 2016-0298, 2018-0159, 2012-0084, 2015-0116, 2015-0233, 2015-0234, 2015-0253
2016-0387
INTRODUCED BY: LARRY COCHRAN, PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO. _____
Title
An ordinance approving and authorizing the execution of Change Order No. 2 for the Willowridge Pump Station Project No. P080905-4A, Willowridge Levee - Phase II, State Project No.H.010102, as part of the West Bank Hurricane Protection Levee Project, to increase the contract amount by $32,895.00 and increase the contract time by fourteen (14) days.
Body
WHEREAS, Ordinance No. 15-8-5 adopted August 3, 2015, by the St. Charles Parish Council, approved and authorized the execution of a contract with Sealevel Construction Inc. for the Willowridge Pump Station Project No. P080905-4A, Willowridge Levee - Phase II, State Project No.H.010102, in the amount of $5,572,160.00; and,
WHEREAS, Ordinance No. 16-9-2 adopted September 21, 2016, by the St. Charles Parish Council, approved and authorized the execution of Change Order #1 to the contract with Sealevel Construction Inc. for the Willowridge Pump Station Project No. P080905-4A, Willowridge Levee - Phase II, State Project No.H.010102, for an increased amount of $60,059.00 and an increase in contract time by forty three (43) days; and,
WHEREAS, Change Order No. 2 is a result of a change within the scope of the contract to install 85 linear feet (2,550 sq ft) of sheet pile at the discharge basin of the pump station to direct the flow of the discharge water into an existing drainage canal; and,
WHEREAS, the increase in the contract amount of $32,895.00 is a result of the addition of one (1) bid line item; and,
WHEREAS, the increase in contract time by fourteen (14) days will result in additional days projected to construct the Willowridge Pump Station.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS,
SECTION I. That Change Order No. 2 for the Willowridge Pump Station Project No. P080905-4A, Willowridge Levee - Phase II, State Project No.H.010102, as part of the West Bank Hurricane Protection Levee Project...

Click here for full text