logo  ST. CHARLES PARISH, LA
File #: 2004-0120    Version: 1 Name: Engineering Services Contract-Barowka & Bonura Engineers & Consultants, L.L.C.-Bar None East Subsurface, Phase III
Type: Ordinance Status: Enacted
File created: 3/22/2004 In control: Parish Council
On agenda: Final action: 4/5/2004
Enactment date: 4/5/2004 Enactment #: 04-4-5
Title: An ordinance to approve and authorize the execution of an Engineering Services Contract with Barowka & Bonura Engineers & Consultants, L.L.C. for the design of Parish Project No. P030615, Bar None East Subsurface, Phase III.
Sponsors: Albert D. Laque, Department of Public Works
Indexes: DRO (Bar None East Subsurface, Ph. III)
Attachments: 1. 2004-0120 Contract-F, 2. 2004-0120 Final Ord 04-4-5 with Contract
Related files: 2002-0133, 2003-0076, 2003-0125, 2003-0314, 2004-0199, 2004-0472
2004-0120
INTRODUCED BY: ALBERT D. LAQUE, PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO.__________
Title
An ordinance to approve and authorize the execution of an Engineering Services Contract with Barowka & Bonura Engineers & Consultants, L.L.C. for the design of Parish Project No. P030615, Bar None East Subsurface, Phase III.
Body
WHEREAS, subsurface drainage improvements are required on Canyon and Holster Lanes from Palamino Drive eastward to the dead end due to improperly sized culverts and inadequate catch basin spacing; and,
WHEREAS, this project design will implement all the necessary changes along the eastern portions of Canyon and Holster Lanes to improve stormwater flows to the eastern drainage ditch of Bar None Ranch Estates; and,
WHEREAS, the QBS Selection Board met on March 3, 2004 and recommended award of Parish Project No. P030615, Bar None East Subsurface, Phase III to Barowka & Bonura Engineers & Consultants, L.L.C. (See Attachment A); and,
WHEREAS, the Probable Project Budget for this contract is as follows:
Construction $ 172,200
Basic Engineering 20,925
Soils Investigation 1,600
Surveying 3,400
Resident Inspection 20,000
Testing/Other 7,500
Total Probable Project Budget $ 225,625
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That the Engineering Services Contract with Barowka & Bonura Engineers & Consultants, L.L.C. for the design of Parish Project No. P030615, Bar None East Subsurface, Phase III be hereby accepted.
SECTION II. That the Parish President is hereby authorized to execute the attached Engineering Services Contract.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:




And the ordinance was declared adopted this ______ day of ____________, 2004, to become effective five (5) days after publication in the Official Journal.



CHAIRMAN:_____________________...