An ordinance to approve and authorize the execution of Change Order No. 1 and final for the Eastbank C Plant Water Treatment Plant Clarifier Refurbishment (Project No. WWKS 60) to increase the contract time by 34 calendar days and to increase the contract amount by $24,058.65.
Body
WHEREAS, Ordinance No. 12-6-13 adopted June 18, 2012, by the St. Charles Parish Council, approved and authorized the execution of a contract with M.R. Pittman Group for the Eastbank C Plant Water Treatment Plant Clarifier Refurbishment (Project No. WWKS 60) in the amount of $1,134,000.00; and,
WHEREAS, it is now necessary to increase the contract time by 34 calendar days and to increase the contract amount by $24,058.65.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That Change Order No. One (1) and final for the Eastbank C Plant Water Treatment Plant Clarifier Refurbishment (Project No. WWKS 60) to increase the contract time by 34 calendar days and to increase the contract amount by $24,058.65 is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this ______ day of __________, 2013, to become effective five (5) days after publication in the Official Journal.
CHAIRMAN:
SECRETARY:
DLVD/PARISH PRESIDENT:
APPROVED: DISAPPROVED:
PARISH PRESIDENT:
RETD/SECRETARY:
AT: RECD BY: