logo  ST. CHARLES PARISH, LA
File #: 2000-0457    Version: 1 Name: Amendment No. 4 to the Professional Services Agreement with Camp Dresser & McKee, Inc. for necessary Consulting Engineering Services associated with Parish Project No. S950301, Eastbank and Westbank Regional Wastewater Treatment Plants and associated Pump
Type: Ordinance Status: Enacted
File created: 9/18/2000 In control: Parish Council
On agenda: Final action: 10/9/2000
Enactment date: 10/9/2000 Enactment #: 00-10-8
Title: An ordinance to approve and authorize the execution of Amendment No. 4 to the Professional Services Agreement with Camp Dresser & McKee, Inc. for necessary Consulting Engineering Services associated with Parish Project No. S950301, Eastbank and Westbank Regional Wastewater Treatment Plants and associated Pumping Stations and Force Mains, to increase the project contingency by $247,000.00.
Sponsors: Brian A. Fabre
Indexes: SPW (EB and WB Regional Wastewater Treatment Plants and Associated Pumping Stations and Force Mains)
Attachments: 1. 2000-0457 Agreement Amendment-Final, 2. AMENDMENT NO4, 3. OUT-OF-SCOPEAmendment No. 4, 4. 2000-0457 Final Ord 00-10-8 with Amendment
Related files: 2000-0594, 2003-0003, 2002-0091, 2001-0007, 2001-0413, 2001-0438, 2006-0379, 2006-0286
2000-0457
INTRODUCED BY: BRIAN A. FABRE
COUNCILMAN, DISTRICT II
ORDINANCE NO. _________
Title
An ordinance to approve and authorize the execution of Amendment No. 4 to the Professional Services Agreement with Camp Dresser & McKee, Inc. for necessary Consulting Engineering Services associated with Parish Project No. S950301, Eastbank and Westbank Regional Wastewater Treatment Plants and associated Pumping Stations and Force Mains, to increase the project contingency by $247,000.00.
Body
WHEREAS, Ordinance No. 95-11-2, adopted November 6, 1995, authorized the execution of a Professional Services Agreement with Camp, Dresser, and McKee, Inc. (CDM) to perform necessary pre-construction, design, bidding, and construction management for the new Destrehan and Hahnville Wastewater Treatment Plants (WWTPs) for a fee of $1,908,289.00; and,
WHEREAS, Ordinance No. 96-8-4, adopted August 5, 1996, added the Montz, Norco, Ama, Paradis, Killona, and Bayou Gauche Lift Stations and associated force mains to the original project scope and increased the total project engineering fees to $3,168,842.00; and,
WHEREAS, Ordinance No. 97-3-2, adopted March 10, 1997, increased the time for resident inspection and construction management, increased the fees for surveying services and fees for the preparation of servitude/permit drawings, and increased the design fee to correspond to construction estimates, thus increasing the total project engineering fees to $4,613,223.00; and,
WHEREAS, Ordinance No. 98-3-14, adopted March 24, 1998, clarified the design and resident inspection fees for the individual project components; and,
WHEREAS, due to the inclusion of out-of-scope work to the original contract at the request of Parish, the contingency fee shall be increased by $247,500 as itemized in the attachment to this Ordinance; and,
WHEREAS, the opinion of probable project budget is amended as follows:
Peer Review 40,000.00
Surveying Services 246,800.00
...