2016-0298
INTRODUCED BY: LARRY COCHRAN, PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO. _____
Title
An ordinance approving and authorizing the execution of Change Order No. 1 for the Willowridge Pump Station Project No. P080905-4A, Willowridge Levee - Phase II, State Project No.H.010102, as part of the West Bank Hurricane Protection Levee Project, to increase the contract amount by $60,059.00 and increase the contract time by forty three (43) days.
Body
WHEREAS, Ordinance No. 15-8-5, adopted August 3, 2015, by the St. Charles Parish Council, approved and authorized the execution of a contract with Sealevel Construction Inc. for the Willowridge Pump Station Project No. P080905-4A, Willowridge Levee - Phase II, State Project No.H.010102, in the amount of $60,059.00; and,
WHEREAS, Change Order No. 1 is a result of a change within the scope of the contract to install a 2" water meter to provide potable water to the Pump Station; increase the capacity of electrical system for equipment power requirements to serve the Pump Station; increase the size of the fenced area securing the Pump Station for access to Pump Station equipment; and,
WHEREAS, the increase in the contract amount of $60,059.00 is a result of the addition of one (1) bid line item and increase in six (6) bid line items; and,
WHEREAS, the increase in contract time by forty three (43) days is a result of additional days projected to construct the Willowridge Pump Station.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS,
SECTION I. That Change Order No. 1 for the Willowridge Pump Station Project No. P080905-4A, Willowridge Levee - Phase II, State Project No.H.010102, as part of the West Bank Hurricane Protection Levee Project, to increase the contract amount by $60,059.00 and increase the contract time by forty three (43) days is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said Change Order No. 1 on behalf of St. Charles Par...
Click here for full text