logo  ST. CHARLES PARISH, LA
File #: 2003-0274    Version: 1 Name: C.O. 2 for Parish Project No. P980701, Willowdale Drainage Pump Station, to increase the contract time by 37 calendar days due to two tropical storms and one hurricane
Type: Ordinance Status: Enacted
File created: 8/4/2003 In control: Parish Council
On agenda: Final action: 8/18/2003
Enactment date: 8/18/2003 Enactment #: 03-8-12
Title: An ordinance approving and authorizing the execution of Change Order No. Two (2) for Parish Project No. P980701, Willowdale Drainage Pump Station, to increase the contract time by 37 calendar days due to two tropical storms and one hurricane.
Sponsors: Albert D. Laque, Department of Public Works
Indexes: DRO (Willowdale Pump Station)
Attachments: 1. 2003-0274 Change Order-F, 2. 2003-0274 Final Ord 03-8-12 with Change Order
Related files: 2001-0307, 2002-0212, 2002-0401, 2003-0158, 2003-0357
2003-0274
INTRODUCED BY: ALBERT D. LAQUE, PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO. _____
Title
An ordinance approving and authorizing the execution of Change Order No. Two (2) for Parish Project No. P980701, Willowdale Drainage Pump Station, to increase the contract time by 37 calendar days due to two tropical storms and one hurricane.
Body
WHEREAS, Ordinance No. 02-6-1 adopted June 3, 2002 by the St. Charles Parish Council, approved and authorized the execution of a contract with D & O Contractors, Inc. for the construction of Willowdale Drainage Pump Station in the amount of $3,091,611.00; and,
WHEREAS, Ordinance No. 02-10-7 adopted October 7, 2002 by the St. Charles Parish Council, approved and authorized Change Order No. One (1) to increase in the size of the triplex station from 360 CFS to 525 CFS to meet the entire West Bank Master Drainage Plan flow of 524 CFS for a construction contract increase of $473,714.00; and,
WHEREAS, Hurricane Lili, Tropical Storm Isadore, and Tropical Storm Bill delayed construction progress during these events and subsequently caused poor site conditions which further hindered construction progress (see attached letters).
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS,
SECTION I. That Change Order No. Two (2) to the contract for the Willowdale Drainage Pump Station to increase the contract time by 37 calendar days is hereby approved.
SECTION II. That the Parish President is hereby authorized to execute said Change Order.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:




And the ordinance was declared adopted this _____ day of ____________, ___, to become effective five (5) days after publication in the Official Journal.



CHAIRMAN:______________________________________________
SECRETARY:_____________________________________________
DLVD/PARISH PRESIDENT:_________________________________
APPROVED:______________ DISAPPROVED:____...