Title: An ordinance to approve and authorize the execution of a contract with Tullier Services, LLC, for Parish Project No. S080503-4; Upgrades to Anna and Ama Lift Stations, with a Base Bid in the amount of $203,000.00 and Alternate Bid in the amount of $11,000.
Sponsors: Lawrence 'Larry' Cochran, Department of Wastewater
Indexes: SPW (Anna and Ama Lift Stations Upgrades)
Attachments: 1. 2017-0308 Contract Anna-Ama LS, 2. 2017-0308 Contract-F, 3. 2017-0308 Final Ord 17-10-4 with Contract, 4. 2017-0308 Notice of Contract-F, 5. 2017-0308 Notice to Proceed-F, 6. 2017-0308 Completion-F
Related files: 2012-0212, 2012-0198, 2010-0446, 2009-0422, 2008-0422, 2018-0210

2017-0308

INTRODUCED BY:                     LARRY COCHRAN, PARISH PRESIDENT

                                                               (DEPARTMENT OF WASTEWATER)

ORDINANCE NO. __________

Title

An ordinance to approve and authorize the execution of a contract with Tullier Services, LLC, for Parish Project No. S080503-4; Upgrades to Anna and Ama Lift Stations, with a Base Bid in the amount of $203,000.00 and Alternate Bid in the amount of $11,000.

Body

WHEREAS,                     sealed bids were received by St. Charles Parish on August 15, 2017 for S080503-4; Upgrades to Anna and Ama Lift Stations; and,

WHEREAS,                     Environmental Engineering Service, Inc, Consulting Engineers for the Project, have reviewed the bids and recommend that the Base Bid and Alternate be awarded in the total amount of $214,000.00 by Tullier Services, LLC be accepted.

THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:

                     SECTION I.                     That the bid of Tullier Services, LLC, for the construction of St. Charles Parish Project No. S080503-4; Upgrades to Anna and Ama Lift Stations, be hereby approved and accepted, in the amount of $214,000.00;

                     SECTION II.                     That the Parish President is hereby authorized to execute said contract documents on behalf of St. Charles Parish.

                     The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:

 

 

 

 

                     And the ordinance was declared adopted this ______ day of __________, 2017, to become effective five (5) days after publication in the Official Journal.

 

 

CHAIRMAN:_________________________________________

SECRETARY:________________________________________

DLVD/PARISH PRESIDENT:____________________________

APPROVED:______________ DISAPPROVED:_____________

 

PARISH PRESIDENT:_________________________________

RETD/SECRETARY:__________________________________

AT:_______________ RECD BY: ________________________