2013-0473
INTRODUCED BY: V.J. St. Pierre, JR., PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO.
Title
An ordinance approving and authorizing the execution of Change Order No. 1 for the St. Charles Parish Courthouse Door and Window Replacement Project, HMPG # 1786-089-0001, FEMA Project #0071, to add additional days to the contract and work in the amount of $8,850.00.
Body
WHEREAS, Ordinance No. 13-3-15 adopted March 25, 2013 by the St. Charles Parish Council awarded construction of the St. Charles Parish Courthouse Door and Window Replacement Project, HMPG # 1786-089-0001, FEMA Project #0071 to Southern Construction of Metairie, LLC; and,
WHEREAS, it is necessary to amend the contract to add the additional work, to adjust the original contract quantities with current quantities resulting in an increase to the contract amount by $8,850.00 and an additional 57 days.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That Change Order No. 1 for the St. Charles Parish Courthouse Door and Window Replacement project, HMPG # 1786-089-0001, FEMA Project #0071, to add additional days to the contract and work in the amount of $8,850.00 is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this _____ day of ___________, 2014, to become effective five (5) days after this publication in the official journal.
CHAIRMAN:
SECRETARY:
DLVD/PARISH PRESIDENT:
APPROVED: DISAPPROVED:
PARISH PRESIDENT:
RETD/SECRETARY:
AT: RECD BY: