File #: 2024-0247    Version: 1 Name: C.O. No. 1 for the Des Allemands Phase 1 Bulkhead (Project No. P210601), to increase the contract amount by $840,457.43 and increase the contract time by eighty-nine (89) calendar days
Type: Ordinance Status: Enacted
File created: 7/8/2024 In control: Parish Council
On agenda: 7/22/2024 Final action: 7/22/2024
Enactment date: Enactment #: 24-7-20
Title: An ordinance approving and authorizing the execution of Change Order No. 1 for the Des Allemands Phase 1 Bulkhead (Project No. P210601), to increase the contract amount by $840,457.43 and increase the contract time by eighty-nine (89) calendar days.
Sponsors: Matthew Jewell, Department of Public Works
Indexes: DRO (Des Allemands Bulkhead - Ph. 1), Public Works (Dept. of)
Attachments: 1. 2024-0247 Change Order Partially Executed, 2. 2024-0247 Final Ord 24-7-20 with change order, 3. 2024-0247 Recordation Documents
Related files: 2021-0213, 2022-0010, 2022-0056, 2022-0237, 2023-0265, 2023-0312
2024-0247
INTRODUCED BY: MATTHEW JEWELL, PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO. ____________
Title
An ordinance approving and authorizing the execution of Change Order No. 1 for the Des Allemands Phase 1 Bulkhead (Project No. P210601), to increase the contract amount by $840,457.43 and increase the contract time by eighty-nine (89) calendar days.
Body
WHEREAS, Ordinance No. 21-8-13 adopted on August 23, 2021, by the St. Charles Parish Council, approved and authorized the execution of a Professional Services Agreement with All South Consulting Engineers, LLC., to perform engineering services for Des Allemands Bulkhead (Project No. P210601), in the amount not to exceed $404,707.00; and,
WHEREAS, Ordinance No. 22-1-8 adopted on January 24, 2022, by the St. Charles Parish Council, approved and authorized the execution of a Contract with APC Construction, LLC, to perform construction services for Des Allemands Emergency Bulkhead (Project No. P210601), in the amount of $1,908,019.20; and,
WHEREAS, Ordinance No. 22-3-6 adopted on March 7, 2022, by the St. Charles Parish Council, approved and authorized the execution of Amendment No. 1 to Ordinance 21-8-13, which approved the Professional Services Agreement with All South Consulting Engineers, LLC, to perform engineering services for the Des Allemands Bulkhead (Parish Project No. P210601), to increase the overall design contract by $322,238.00, bringing the overall contract value to $726,945.00; and,
WHEREAS, Ordinance No. 22-9-4 adopted on September 19, 2022, by the St. Charles Parish Council, approved and authorized the execution of Change Order No. 1 to the Contract for Des Allemands Emergency Bulkhead (Project No. P210601), decreasing the overall contract by $135,101.22 and 36 calendar days, resulting in an overall contract value of $1,772,917.98 and 144 calendar days; and,
WHEREAS, Ordinance No. 23-10-5 adopted on October 9, 2023, by the St. Charles Parish Council, approved and authorized the ...