File #: 2003-0025    Version: 1 Name: Change Order No. One (1)-Dunleith Canal Bank Stabilization - Phase VI,
Type: Ordinance Status: Enacted
File created: 1/21/2003 In control: Parish Council
On agenda: Final action: 2/3/2003
Enactment date: 2/3/2003 Enactment #: 03-2-4
Title: An ordinance approving and authorizing the execution of Change Order No. One (1) for Parish Project No. P011009, Dunleith Canal Bank Stabilization - Phase VI, to increase the contract time by 38 days.
Sponsors: Albert D. Laque, Department of Public Works
Indexes: DRO (Dunleith Canal Bank Stab., Ph. VI)
Attachments: 1. 2003-0025 Change Order-F, 2. 2003-0025 Final Ord 03-2-4 with Change Order
Related files: 2000-0505, 2001-0219, 2002-0396, 2003-0199, 2008-0481, 2010-0277, 2011-0021, 2011-0296, 2012-0211, 2012-0418, 2013-0211, 2014-0348, 2014-0402, 2015-0049, 2015-0339, 2018-0066, 2017-0216, 2015-0311, 2020-0101, 2015-0150, 2015-0241, 2016-0247, 2016-0299, 2019-0265, 2019-0347, 2020-0313
2003 - 0025
INTRODUCED BY:      ALBERT D. LAQUE, PARISH PRESIDENT
                  (DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO.                          
Title
An ordinance approving and authorizing the execution of Change Order No. One (1) for Parish Project No. P011009, Dunleith Canal Bank Stabilization - Phase VI, to increase the contract time by 38 days.
Body
WHEREAS,      Ordinance No. 02-10-3, adopted on October 7, 2002, by the St. Charles Parish Council awarded construction of Parish Project No. P011009, Dunleith Canal Bank Stabilization-Phase VI, to Beverly Construction, Co., L.L.C.; and,
WHEREAS,      the project site was too saturated to allow heavy equipment from the date of the Notice to Proceed, December 6, 2002, until January 13, 2003 for a total delay of 38 days; and,
WHEREAS,      to give Beverly Construction, Co., L.L.C. adequate time to complete the project, an increase of 38 days in the contract time is necessary.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I.      That the Administration is hereby authorized to execute Change Order No. One (1) for the Dunleith Canal Bank Stabilization-Phase VI contract to increase the contract time by 38 days.
      SECTION II.      That the Parish President is hereby authorized to execute said Change Order.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
 
 
 
 
And the ordinance was declared adopted this            day of                       , 2003, to become effective five (5) days after publication in the Official Journal.
Dunleith Canal Bank Stabilization - Phase VI
 
 
 
 
CHAIRMAN:______________________________________________
SECRETARY:_____________________________________________
DLVD/PARISH PRESIDENT:_________________________________
APPROVED:______________ DISAPPROVED:__________________
 
PARISH PRESIDENT:______________________________________
RETD/SECRETARY:_______________________________________
AT:_______________RECD BY: _____________________________