File #: 2013-0373    Version: 1 Name: Change Order No. 1 for West Bank Multi-Use Path Phase III
Type: Ordinance Status: Enacted
File created: 10/7/2013 In control: Parish Council
On agenda: Final action: 10/21/2013
Enactment date: 10/21/2013 Enactment #: 13-10-16
Title: An ordinance approving and authorizing the execution of Change Order No. 1 for Parish Project No P020903, West Bank Multi-Use Path Phase III, State Project No. H.007552, Federal Aid Project No. 4510(500) to add additional work in the amount of $151,603.68 and to increase the contract time by thirty (30) working days.
Sponsors: V.J. St. Pierre Jr., Department of Public Works
Indexes: P and R (Dept. of) (WB Bike Path)
Attachments: 1. Change Order for WB Multi-Use Path Phase III.pdf, 2. 2013-0373 Change Order-F, 3. 2013-0373 Final Ord 13-10-16 with Change Order
Related files: 2011-0023, 2009-0106, 2006-0153, 2003-0060, 2011-0166, 2012-0128, 1999-5027, 2002-0069, 2003-0253, 2004-0276, 2005-0193, 2003-0397, 2009-0198, 2009-0364, 2006-0238, 2007-0316, 2009-0145, 2009-0278, 2009-0487, 2010-0132, 2002-0342, 2005-0202, 2009-0307, 2009-0467, 2010-0154, 2010-0370, 2012-0093, 2014-0334, 2015-0012, 2015-0013, 2017-0409, 2015-0390, 2016-0417, 2018-0145, 2020-0347, 2018-0183
2013-0373
INTRODUCED BY: V.J. St. Pierre, PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO.
Title
An ordinance approving and authorizing the execution of Change Order No. 1 for Parish Project No P020903, West Bank Multi-Use Path Phase III, State Project No. H.007552, Federal Aid Project No. 4510(500) to add additional work in the amount of $151,603.68 and to increase the contract time by thirty (30) working days.
Body
WHEREAS, Ordinance No. 12-3-1 adopted March 12, 2012 by the St. Charles Parish Council awarded construction of Parish Project No P020903, West Bank Multi-Use Path Phase III, State Project No. H.007552, Federal Aid Project No. 4510(500), to Barriere Construction Co., LLC; and,
WHEREAS, it is necessary to amend the contract to add the additional work and to adjust the original contract quantities with current quantities resulting in an increase to the contract amount by $151,603.68 and an increase in thirty (30) working days; and,
WHEREAS, this will allow St. Charles Parish to utilize the full Federal funds of $881,700 available on the project.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That Change Order No. 1 for Parish Project No P020903, West Bank Multi-Use Path Phase III, State Project No. H.007552, Federal Aid Project No. 4510(500), to increase the contract amount by $151,603.68 and to increase the contract time by thirty (30) working days, is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:




And the ordinance was declared adopted this ______ day of __________, 2013, to become effective five (5) days after this publication in the official journal.


CHAIRMAN:
SECRETARY:
DLVD/PARISH PRESIDENT:
APPROVED: DISAPPROVED:

PARISH PRESIDENT:
...

Click here for full text