logo  ST. CHARLES PARISH, LA
File #: 2015-0241    Version: Name: C.O. No. 1 for Parish Project No. P081102-5, Dunleith Canal Bank Stabilization Phase 4, to increase contract amount by $15,304.62 and increase contract time by 45 days
Type: Ordinance Status: Enacted
File created: 7/6/2015 In control: Parish Council
On agenda: 7/20/2015 Final action: 7/20/2015
Enactment date: Enactment #: 15-7-15
Title: An ordinance approving and authorizing the execution of Change Order No. 1 for Parish Project No. P081102-5, Dunleith Canal Bank Stabilization Phase 4, to increase contract amount by $15,304.62 and increase contract time by 45 days.
Sponsors: V.J. St. Pierre Jr., Department of Public Works
Indexes: DRO (Dunleith Canal Stab., Ph. 4)
Attachments: 1. 2015-0241 Dunleith Canal - Ph IV C.O. No. 1, 2. 2015-0241 Change Order-F, 3. 2015-0241 Final Ord 15-7-15 with Change Order
Related files: 2015-0150, 2015-0049, 2012-0418, 2013-0211, 2014-0348, 2014-0402, 2002-0396, 2003-0025, 2003-0199, 2008-0481, 2010-0277, 2011-0021, 2011-0296, 2012-0211, 2000-0505, 2001-0219, 2015-0311, 2019-0265, 2016-0247, 2018-0066, 2020-0101, 2020-0313, 2015-0339, 2016-0299, 2017-0216, 2019-0347

2015-0241

INTRODUCED BY:                     V.J. St. Pierre, JR., PARISH PRESIDENT

                                                               (DEPARTMENT OF PUBLIC WORKS)

ORDINANCE NO.                                                                 

Title

An ordinance approving and authorizing the execution of Change Order No. 1 for Parish Project No. P081102-5, Dunleith Canal Bank Stabilization Phase 4, to increase contract amount by $15,304.62 and increase contract time by 45 days.

Body

WHEREAS,                     Ordinance No. 14-12-12 adopted December 15, 2014 by the St. Charles Parish Council awarded construction of Parish Project No. P081102-5, Dunleith Canal Bank Stabilization Phase 4, to Circle Construction Company, LLC in the amount of $1,427,563.00; and,

WHEREAS,                     it is necessary to extend the sheet piling by an additional 104 linear feet to protect the Dunleith Canal west side bank between the Shell Pipeline and Carriage Canal; and,

WHEREAS,                     this additional work will be offset by changes as described in the change order resulting in an increase in the contract amount by $15,304.62 and increase in the contract time by 45 days.

THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:

                     SECTION I.                     That Change Order No. 1 for Parish Project No. P081102-5, Dunleith Canal Bank Stabilization Phase 4, increase contract amount by $15,304.62 and increase contract time by 45 days is hereby approved and accepted.

                     SECTION II.                     That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.

                     The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:

 

 

 

 

                     And the ordinance was declared adopted this ______ day of __________, 2015, to become effective five (5) days after this publication in the official journal.

 

 

CHAIRMAN:                                                                                                                               

SECRETARY:                                                                                                                               

DLVD/PARISH PRESIDENT:                                                                                     

APPROVED:                       DISAPPROVED:                                           

 

PARISH PRESIDENT:                                                                                                          

RETD/SECRETARY:                                                                                                           

AT:                        RECD BY: