File #: 2003-0125    Version: 1 Name: Engineering Services Contract-Digital Engineering & Imaging, Inc.-Bar None East Subsurface, Phase II.Imaging, Inc.
Type: Ordinance Status: Enacted
File created: 4/7/2003 In control: Parish Council
On agenda: Final action: 4/21/2003
Enactment date: 4/21/2003 Enactment #: 03-4-20
Title: An ordinance to approve and authorize the execution of an Engineering Services Contract with Digital Engineering & Imaging, Inc. for the design of Parish Project No. P011002, Bar None East Subsurface, Phase II.
Sponsors: Albert D. Laque, Department of Public Works
Indexes: DRO (Bar None East Subsurface, Ph. II)
Attachments: 1. 2003-0125 Contract-F, 2. 2003-0125 Final Ord 03-4-20 with Contract
Related files: 2004-0120, 2004-0472, 2003-0314, 2002-0133, 2003-0076, 2004-0199
2003-0125
INTRODUCED BY: ALBERT D. LAQUE, PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO.__________
Title
An ordinance to approve and authorize the execution of an Engineering Services Contract with Digital Engineering & Imaging, Inc. for the design of Parish Project No. P011002, Bar None East Subsurface, Phase II.
Body
WHEREAS, subsurface drainage improvements are required on Chuckwagon and Bridlepath Lanes from Palamino Drive eastward to the dead end due to improperly sized culverts and inadequate catch basin spacing; and,
WHEREAS, this project design will implement all the necessary changes along the eastern portions of Bridlepath and Chuckwagon Lanes to improve stormwater flows to the eastern drainage ditch of Bar None Ranch Estates; and,
WHEREAS, the QBS Selection Board met on February 26, 2003 and recommended award of Parish Project No. P011002, Bar None East Subsurface, Phase II to Digital Engineering & Imaging, Inc. (See Attachment A); and,
WHEREAS, the Probable Project Budget for this contract is as follows:
Construction $ 150,100
Basic Engineering 35,500
Soils Investigation 1,500
Surveying 3,000
Resident Inspection 19,000
Testing/Other 6,500
Total Probable Project Budget $ 215,600
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That the Engineering Services Contract with Digital Engineering & Imaging, Inc. for the design of Parish Project No. P011002, Bar None East Subsurface, Phase II be hereby accepted.
SECTION II. That the Parish President is hereby authorized to execute the attached Engineering Services Contract.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:




And the ordinance was declared adopted this ______ day of ____________, 2003, to become effective five (5) days after publication in the Official Journal.


CHAIRMAN:______________________________________________