2000-0313
INTRODUCED BY: ALBERT D. LAQUE, PARISH PRESIDENT
(DEPARTMENT OF WASTEWATER)
ORDINANCE NO. ______
Title
An ordinance to approve payment for invoices pending for professional design services performed by Environmental Engineering Services, Inc. for the Paradis Force Main Project No. S980104 in the amount of $10,600.00.
Body
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That the Department of Public Works/Wastewater has requested and authorized Environmental Engineering Services, Inc. to redesign portions of the Paradis Force Main; and,
SECTION II. That the Department of Public Works/Wastewater had entered into an administrative contract with Environmental Engineering Services, Inc. to design the Paradis Force Main and that this work had been completed and accepted; and,
SECTION III. That the redesign of the Paradis Force Main is out of the scope-of-services of Environmental Engineering Services, Inc.'s contract; the amount of the redesign services totaling $10,600.00.
NOW, THEREFORE, BE IT ORDAINED, THAT WE, THE MEMBERS OF THE
ST. CHARLES PARISH COUNCIL, do hereby authorize the payment of invoices to Environmental Engineering Services, Inc. for the sum of $10,600.00 for work performed out of the scope-of-work of its existing contract for design services for the Paradis Force Main Project.
vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as
follows:
And the ordinance was declared adopted this ______ day of ____________, ____,
to become effective five (5) days after publication in the Official Journal.
CHAIRMAN: _______________________________________
SECRETARY:______________________________________
DLVD/PARISH PRESIDENT:
APPROVED:_____________DISAPPROVED:
PARISH PRESIDENT
RETD/SECRETARY:
AT:__________________RECD BY: