An ordinance approving and authorizing the execution of Change Order No. 1 with for the Ormond CN Railway Culverts Project (Project No. P200801), to increase the contract amount by $1,005,921.76 and increase the contract time by sixty (60) days.
Body
WHEREAS, Ordinance No. 20-9-5 adopted on September 21, 2020, by the St. Charles Parish Council, approved and authorized the execution of engineering services agreement with Barowka and Bonura Engineers & Consultants (BBEC), LLC for providing all necessary services for the Ormond Railroad Culverts Project (P200801), in the amount of $331,520.00; and,
WHEREAS, Ordinance No. 26-1-4 adopted on January 12, 2026, by the St. Charles Parish Council, approved and authorized the execution of a Professional Services Agreement with Barowka and Bonura Engineers & Consultants (BBEC), LLC, to perform engineering services for the Ormond CN Railway Culverts (Project No. P200801), in the not to exceed amount of $1,097,231.00; and,
WHEREAS, Ordinance No. 25-7-9 adopted on July 21, 2025, by the St. Charles Parish Council, approved and authorized the execution of a Contract with BLD Services, LLC, for the Ormond CN Railway Culverts Project (Project No. P200801), in the amount of $10,542,425.00; and,
WHEREAS, it is necessary to amend the construction contract for Ormond CN Railways Culverts Project (Project No. P200801), as major utility conflicts required additional work and work items; and,
WHEREAS, St. Charles Parish and BLD Services, LLC, have mutually agreed to increase the contract amount by $1,005,921.76 and increase the contract time by sixty (60) days.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That Change Order No. 1 for the Ormond CN Railways Culverts Project (Project No. P200801), to increase the contract amount by $1,005,921.76 and increase the contract time by sixty (...