An ordinance to approve and authorize the execution of Change Order No. 1 (Final) for the construction of Federal Project No. 22-00876, Killona Park Development, Phase III, to increase the contract time by fifty-three (53) days.
Body
WHEREAS, Ordinance No. 11-7-1, adopted July 11, 2011, by the St. Charles Parish Council, approved and authorized the execution of a contract with Frickey Brothers Construction, LLC for the construction of Federal Project No. 22-00876, Killona Park Development, Phase III, in the amount of $144,873.00; and,
WHEREAS, the increase in contract time was a result of delays in approval, ordering and shipment of specialty items (lighting fixtures and bulbs) causing a delay in the installation of the lighting for the baseball fields.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That Change Order No. 1 (Final) for the construction of Federal Project No. 22-00876, Killona Park Development, Phase III, to increase the contract time by fifty-three (53) days is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this day of , 2012, to become effective five (5) days after publication in the Official Journal.
CHAIRMAN:
SECRETARY:
DLVD/PARISH PRESIDENT:
APPROVED: DISAPPROVED:
PARISH PRESIDENT:
RETD/SECRETARY:
AT: RECD BY: