logo  ST. CHARLES PARISH, LA
File #: 2004-0064    Version: 1 Name: Change Order West Bank Hurricane Protection Levee Clearing and Grubbing, Phase I
Type: Ordinance Status: Enacted
File created: 2/2/2004 In control: Parish Council
On agenda: Final action: 2/16/2004
Enactment date: 2/16/2004 Enactment #: 04-2-12
Title: An ordinance approving and authorizing the execution of Change Order One (1) for Parish Project No. P030908, West Bank Hurricane Protection Levee Clearing and Grubbing, Phase I, to decrease the contract amount by $76,000.00.
Sponsors: Albert D. Laque, Department of Public Works
Indexes: Hurricane Protection Levee (WB - Magnolia Ridge Ph. 1, Clearing and Grubbing)
Attachments: 1. 2004-0064 Change Order, 2. 2004-0064 Final Ord 04-2-12 with Change Order
Related files: 2020-0176, 2020-0081, 2014-0280, 2016-0076, 2016-0214, 2018-0305, 2001-0177, 1999-4758, 2001-0388, 2002-0279, 2004-0063, 2007-0333, 2013-0443, 2014-0041, 2006-0046, 2006-0054, 2008-0212, 2010-0318, 2004-0483, 2008-0417, 2008-0418, 2009-0147, 2013-0442

2004-0064

INTRODUCED BY:                     ALBERT D. LAQUE, PARISH PRESIDENT

                                                               (DEPARTMENT OF PUBLIC WORKS)

ORDINANCE NO.:                                                                

Title

An ordinance approving and authorizing the execution of Change Order One (1) for Parish Project No. P030908, West Bank Hurricane Protection Levee Clearing and Grubbing, Phase I, to decrease the contract amount by $76,000.00.

body

WHEREAS,                     Ordinance No.   04-2-11                     , adopted February 16, 2004 by the St. Charles Parish Council, approved and authorized the execution of a contract with Grillot Construction Co., L.L.C. for the construction of Parish Project No. P030908, West Bank Hurricane Protection Levee Clearing and Grubbing, Phase I; and

WHEREAS,                     Change Order No. One (1) is necessary since Grillot Construction Co., L.L.C. will not require as many construction access roads as originally anticipated.

THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:

SECTION I.                     That the Administration is hereby authorized to execute Change Order No. One (1) for Parish Project No. P030908, West Bank Hurricane Protection Levee Clearing and Grubbing, Phase I, to decrease the overall contract amount by $76,000.00.

                     SECTION II.                     That the Parish President is hereby authorized to execute said Change Order.

The foregoing Ordinance having been submitted to a vote, the vote thereon was as follows:

 

 

 

 

And the ordinance was declared adopted this                                            day of                                           , 2004, to become effective five (5) days after this publication in the official journal.

 

 

CHAIRMAN:_________________________________________

SECRETARY:________________________________________

DLVD/PARISH PRESIDENT:____________________________

APPROVED:______________ DISAPPROVED:_____________

 

PARISH PRESIDENT:_________________________________

RETD/SECRETARY:__________________________________

AT:_______________ RECD BY: ________________________