logo  ST. CHARLES PARISH, LA
File #: 2003-0123    Version: 1 Name: Engineering Services Contract with GSE Associates, Parishwide Telemetry, Phase III
Type: Ordinance Status: Enacted
File created: 4/7/2003 In control: Parish Council
On agenda: Final action: 4/21/2003
Enactment date: 4/21/2003 Enactment #: 03-4-18
Title: An ordinance to approve and authorize the execution of an Engineering Services Contract with GSE Associates, Inc. for the design of Parish Project No. P000303, Parishwide Telemetry, Phase III.
Sponsors: Albert D. Laque, Department of Public Works
Indexes: DRO (Telemetry Ph. III)
Attachments: 1. 2003-0123 Contract-F, 2. 2003-0123 Final Ord 03-4-18 with Contract
Related files: 2004-0286, 2004-0285, 2004-0284, 2000-0282, 2001-0218, 2001-0010, 2001-0444, 2001-0247, 2005-0200, 2005-0225, 2005-0224
2003-0123
INTRODUCED BY: ALBERT D. LAQUE, PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO.__________
Title
An ordinance to approve and authorize the execution of an Engineering Services Contract with GSE Associates, Inc. for the design of Parish Project No. P000303, Parishwide Telemetry, Phase III.
Body
WHEREAS, St. Charles Parish is in the process of implementing telemetry at all drainage pump stations; and,
WHEREAS, this project will install upgrades to the telemetry systems at Cousin's, Eighty Arpent, Destrehan I, and Destrehan II Pump Stations and full telemetry installations at Lakewood, Willowdale I, and Diane Pump Stations; and,
WHEREAS, the QBS Selection Board met on February 26, 2003 and recommended award of Parish Project No. P000303, Parishwide Telemetry, Phase III to GSE Associates, Inc. (See Attachment A); and,
WHEREAS, the Probable Project Budget for this contract is as follows:
Construction $ 485,000
Basic Engineering 42,000
Survey 10,000
Resident Inspection 60,000
Testing 13,000
Geotechnical/Other 13,000
Total Probable Project Budget $ 623,000
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That the Engineering Services Contract with GSE Associates, Inc. for the design of Parish Project No. P000303, Parishwide Telemetry, Phase III be hereby accepted.
SECTION II. That the Parish President is hereby authorized to execute the attached Engineering Services Contract.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:




And the ordinance was declared adopted this ______ day of ____________, 2003, to become effective five (5) days after publication in the Official Journal.


CHAIRMAN:______________________________________________
SECRETARY:_____________________________________________
DLVD/PARISH PRESIDENT:_________________________________
APPROVED:______________ DISAPPROVED:____________...

Click here for full text