An ordinance approving and authorizing the execution of Change Order No. 2 (Final) for Parish Project No. S080501-1, Destrehan WWTP Rehabilitation Phase I Headworks to decrease the contract amount by $19,402.00.
Body
WHEREAS, Ordinance No. 08-12-2, adopted December 1, 2008, by the St. Charles Parish Council, approved and authorized the execution of a contract with Cajun Constructors, Inc. for Destrehan WWTP Rehabilitation Phase I Headworks in the amount of $349,500.00; and,
WHEREAS, Change Order 1 increased the contract amount to $369,493.00 to pay for the repair of unforeseen concrete damage beyond two inches of depth; and,
WHEREAS, it is necessary to finally amend the contract, deleting one item, and adding to another item, resulting in a decrease in the contract of $19,402.00.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. To approve and authorize the execution of Change Order No. 2 (Final) for Parish Project No. S080501-1, Destrehan WWTP Rehabilitation Phase I Headworks to decrease the contract amount by $19,402.00.
SECTION II. That the Parish President is hereby authorized to execute said Change Order.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this _____ day of ___________, 2009, to become effective five (5) days after publication in the Official Journal.
Destrehan WWTP Change Order#2.doc
CHAIRMAN: _________________________________
SECRETARY: ________________________________
DLVD/PARISH PRESIDENT: ____________________
APPROVED: ________ DISAPPROVED: __________
PARISH PRESIDENT: _________________________
RETD/SECRETARY: __________________________
AT: _______________ RECD BY: ________________