2017-0262
INTRODUCED BY: LARRY COCHRAN, PARISH PRESIDENT
(DEPARTMENT OF WATERWORKS)
ORDINANCE NO. ______________
Title
An ordinance to approve and authorize the execution of Change Order No. 1 for the West Bank “A” Plant Clarifier Refurbishment (Project No. WWKS 90) to increase the contract time by 90 calendar days and to increase the contract amount by $117,606.01.
Body
WHEREAS, Ordinance No. 17-4-2 adopted April 3, 2017, by the St. Charles Parish Council, approved and authorized the execution of a contract with Pintail Contracting Services, LLC for the West Bank “A” Plant Clarifier Refurbishment (Project No. WWKS 90) in the amount of $157,100.00; and,
WHEREAS, it is now necessary to increase the contract time by 90 calendar days and to increase the contract amount by $117,606.01.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That Change Order No. One (1) for the West Bank “A” Plant Clarifier Refurbishment (Project No. WWKS 90) to increase the contract time by 90 calendar days and to increase the contract amount by $117,606.01 is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this day of , 2017, to become effective five (5) days after publication in the Official Journal.
CHAIRMAN:_________________________________________
SECRETARY:________________________________________
DLVD/PARISH PRESIDENT:____________________________
APPROVED:______________ DISAPPROVED:_____________
PARISH PRESIDENT:_________________________________
RETD/SECRETARY:__________________________________
AT:_______________ RECD BY: ________________________