2002-0528
INTRODUCED BY: ALBERT D. LAQUE, PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO.__________
Title
An ordinance to approve and authorize the execution of a contract with Gilmore & Son Construction Corporation for the construction of Project P000502, Ormond Trace Stabilization, in the amount of $631,830.00.
Body
WHEREAS, sealed bids were received by the Parish on December 13, 2002, for Ormond Trace Stabilization; and,
WHEREAS, Burk-Kleinpeter, Inc., Consulting Engineer for the Project, has reviewed the bids and recommend that the Contract be awarded to the low bidder, Gilmore & Son Construction Corporation, in the amount of $631,830.00.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That the bid of Gilmore & Son Construction Corporation for the construction of Ormond Trace Stabilization be hereby accepted in the amount of $631,830.00.
SECTION II. That the Parish President is hereby authorized to execute the attached contract documents.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this ______ day of ____________, 2003, to become effective five (5) days after publication in the Official Journal.
CHAIRMAN:______________________________________________
SECRETARY:_____________________________________________
DLVD/PARISH PRESIDENT:_________________________________
APPROVED:______________ DISAPPROVED:__________________
PARISH PRESIDENT:______________________________________
RETD/SECRETARY:_______________________________________
AT:_______________ RECD BY: _____________________________