logo  ST. CHARLES PARISH, LA
File #: 2019-0164    Version: 1 Name: Professional Services Agreement for Montz Master Drainage Plan Implementation with GCR Inc. for the acquisitions of servitude, fee simple parcels, and permitting
Type: Ordinance Status: Enacted
File created: 5/20/2019 In control: Parish Council
On agenda: 6/3/2019 Final action: 6/3/2019
Enactment date: Enactment #: 19-6-4
Title: An ordinance approving and authorizing the execution of a Professional Services Agreement for Parish Project No P080802 Montz Master Drainage Plan Implementation with GCR Inc. to provide professional services regarding the acquisitions of servitude, fee simple parcels, and permitting.
Sponsors: Lawrence 'Larry' Cochran, Department of Public Works
Indexes: DRO (Montz Drg. Plan Implementation), Public Works (Dept. of)
Attachments: 1. 2019-0164 GCR Permiting Prof Service Contract MONTZ -Revised, 2. 2019-0164 Exhibit A, 3. 2019-0164 Final Ord 19-6-4 with agreement, 4. 2019-0164 Email 4-12-23
Related files: 2008-0249, 2008-0441, 2008-0482, 2009-0123, 2010-0414, 2011-0201, 2011-0354, 2012-0076, 2012-0186, 2012-0199, 2012-0297, 2013-0002, 2013-0157, 2014-0001, 2014-0016, 2015-0008, 2015-0009, 2015-0087, 2018-0033, 2018-0342, 2019-0098, 2020-0177, 2021-0053, 2020-0344, 2020-0042, 2021-0140
2019-0164
INTRODUCED BY: LARRY COCHRAN, PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO.
Title
An ordinance approving and authorizing the execution of a Professional Services Agreement for Parish Project No P080802 Montz Master Drainage Plan Implementation with GCR Inc. to provide professional services regarding the acquisitions of servitude, fee simple parcels, and permitting.
Body
WHEREAS, Ordinance No. 16-7-7, adopted July 18, 2016 by the St. Charles Parish Council approved a Professional Services Agreement with GCR Inc. to provided professional services in the acquisition of servitudes and fee simple parcels; and,
WHEREAS, Ordinance No. 18-7-15, adopted July 23, 2018 by the St Charles Parish Council, amended Ordinance 16-7-7 to include work on title research and legal coordination for expropriation and to increase the contract time in one (1) year increments up to three (3) years; and,
WHEREAS, the current Professional Services Agreement, as amended, is to expire on July 20, 2019 and professional services are still required; and,
WHEREAS, Public Works desires to expand upon Parish Project No P080802 Montz Master Drainage Plan Implementation necessitating a new Professional Services Agreement with GCR Inc.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That a Professional Services Agreement for Parish Project No P080802 Montz Master Drainage Plan Implementation with GCR Inc. to provide professional services regarding the acquisitions of servitude, fee simple parcels, and permitting is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said Professional Services Agreement on behalf of St. Charles Parish.
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:



And the ordinance was declared adopted this ______ day of ________, 2019, to become effective five (5) days after this publication in the official journal.


CHAIRMAN:
...

Click here for full text