2002-0221
INTRODUCED BY: ALBERT D. LAQUE, PARISH PRESIDENT
(ADMINISTRATIVE OFFICER)
ORDINANCE NO.
Title
An ordinance to approve and authorize the execution of a contract with Angelo Iafrate Construction, L.L.C., for the East Bank Bike & Pedestrian Path, Phase A & B, State Project No. 744-45-003, Federal Aid Project No. ENH-4500(503).
Body
WHEREAS, the Louisiana Department of Transportation & Development received sealed bids on April 24, 2002, for the East Bank St. Charles Parish Bike & Pedestrian Path, Phase A & B; and,
WHEREAS, the low bid was submitted by Angelo Iafrate Construction, L.L.C., in the amount of $1,054,438.05; and,
WHEREAS, the bid has been approved by the Louisiana Department of Transportation & Development and the Federal Highway Administration; and,
WHEREAS, it is the desire of the Parish Council to award said bid.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That the bid of Angelo Iafrate Construction, L.L.C. for the St. Charles Bike & Pedestrian Path, Phase A & B in the amount of $1,054,438.05 is hereby accepted.
SECTION II. That the Parish President is hereby authorized to execute said contract on behalf of St. Charles Parish.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this day of , 2002, to become effective five (5) days after publication in the Official Journal.
Contract East Bank Bike Path
CHAIRMAN:
SECRETARY:
DLVD/PARISH PRESIDENT:
APPROVED: DISAPPROVED:
PARISH PRESIDENT:
RETD/SECRETARY:
AT: RECD BY: