File #: 2022-0061    Version: 1 Name: C.O. No. 1 for Parish Project No S170601, Luling Oxidation Pond Rehabilitation and Upgrades
Type: Ordinance Status: Enacted
File created: 3/7/2022 In control: Parish Council
On agenda: 3/21/2022 Final action: 3/21/2022
Enactment date: Enactment #: 22-3-10
Title: An ordinance approving and authorizing the execution of Change Order No. 1 for Parish Project No S170601, Luling Oxidation Pond Rehabilitation and Upgrades, to increase the contract amount by $489,238.60, and increase the contract time by 199 days.
Sponsors: Matthew Jewell, Department of Public Works/Wastewater
Indexes: SPW (Luling Oxidation Pond) (Rehab. and Upgrades)
Attachments: 1. 2022-0061 Luing Pond Change Order 1 Final w Signatures, 2. 2022-0061 Final Ord 22-3-10 with Change Order.pdf
Related files: 2017-0228, 2020-0186, 2005-0190, 2009-0075, 2017-0410, 2019-0249, 2000-0525, 2004-0283, 2005-0364, 2005-0365, 2006-0055, 2006-0143, 2021-0185, 2021-0197, 2001-0282, 2000-0284, 2020-0250, 2021-0157, 2023-0122
2022-0061
INTRODUCED BY: MATTHEW JEWELL, PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS/WASTEWATER)
ORDINANCE NO.
Title
An ordinance approving and authorizing the execution of Change Order No. 1 for Parish Project No S170601, Luling Oxidation Pond Rehabilitation and Upgrades, to increase the contract amount by $489,238.60, and increase the contract time by 199 days.
Body
WHEREAS, Ordinance No. 17-7-17 adopted July 31, 2017, by the St. Charles Parish Council approved and authorized the execution of a Contract for professional engineering services with Glenn G. Shaheen & Associates, Inc. (GSA) for Parish Project No. S170601 Luling Oxidation Pond Rehabilitation and Upgrades; and,
WHEREAS, Ordinance No. 20-9-4 adopted September 21, 2020, by the St. Charles Parish Council awarded construction of Parish Project No. S170601, Luling Oxidation Pond Rehabilitation and Upgrades to BLD Services, LLC; and,
WHEREAS, Ordinance No. 21-6-13 adopted June 7, 2021, by the St. Charles Parish Council approved and authorized the execution of Amendment No. 1 to Ordinance No. 17-7-17, Single Project Contract for engineering services with GSA Consulting Engineers, Inc. for Parish Project No. S170601 Luling Oxidation Pond Rehabilitation and Upgrades; and,
WHEREAS, it is necessary to amend the contract by adjusting the contract quantities with requested and necessary work resulting in an increase to the contract amount by $489,238.60, and increase the number of contract calendar days by 199.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That Change Order No. 1 for Parish Project No. S170601, Luling Oxidation Pond Rehabilitation and Upgrades, to increase the contract amount by $489,238.60 and increase the contract time by 199 days is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said Change Order No. 1 on behalf of St. Charles Parish.
The foregoing ordinance having been submitted to a vote, the vote th...