An ordinance approving and authorizing the execution of Change Order No. 1 for DQSI, LLC, for PO-43a LaBranche Salinity Barrier Project, to increase the contract amount by $26,357.85.
Body
WHEREAS, Ordinance No. 15-8-10 adopted August 17, 2015 by the St. Charles Parish Council awarded construction of the PO-43a LaBranche Salinity Barrier Project to DQSI, LLC.; and,
WHEREAS, due to the withdrawal of the original grant receiver subsequent reauthorization of the grant from the Louisiana Coastal Restoration and Protection Authority the project has experience well over a year delay on starting; and,
WHEREAS, because of the delay, the contractor incurred expenses related to keeping the require insurance active over an extended period of time; and,
WHEREAS, unforeseen project site conditions have necessitated the need for a survey of the site; and,
WHEREAS, the Project Engineer has recommended that both these items be addressed as a change order.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That Change Order No. 1 for DQSI, LLC, for PO-43a LaBranche Salinity Barrier Project, to increase the contract amount by $26,357.85 is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this day of , 2018, to become effective five (5) days after publication in the Official Journal.
CHAIRMAN:
SECRETARY:
DLVD/PARISH PRESIDENT:
APPROVED: DISAPPROVED:
PARISH PRESIDENT:
RETD/SECRETARY:
AT: RECD BY: